Design & Cost Report for Park Spring Primary School Expansion, Capital Scheme Number: 32450/PAR/000

10/01/2017 - Design & Cost Report for Park Spring Primary School Expansion, Capital Scheme Number: 32450/PAR/000

The Director of Children’s Services agreed to:

 

  i.  Approve the Design and Cost Report for the second phase of enabling works to provide temporary hard play to facilitate the main scheme at Park Spring Primary School, the cost being £280k, with the appropriate details of the programme, design and cost as set out in this report.

 

  ii.  Approve entering into an Early Works Agreement with Clugston Construction Limited for £280k.

 

  iii.  Note that Authority to Spend was approved for capital of £278k and revenue of £157k on 14/06/16 for enabling works (temporary accommodation) to facilitate the permanent expansion.

 

  iv.  Note a separate DCR for the main works will follow in late January 2017.

 

  v.  Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery.