Issue - decisions

Design & Cost Report for the Universal Infant Free School Meals Project at Thorner C/E Primary School 2016 Capital Scheme Number: 32014/EXP/TNR

09/05/2016 - Design & Cost Report for the Universal Infant Free School Meals Project at Thorner C/E Primary School 2016 Capital Scheme Number: 32014/EXP/TNR

The Head of Learning Systems agreed to:
* approve the proposal to carry out essential kitchen improvement works to address urgent health & safety issues at Thorner C/E Primary School;
* approve the procurement strategy to utilise competitive tendering methods in accordance with CPR 3.1.8;
* authorise expenditure in the sum of £180,401.00 from capital scheme number 32014/EXP/TNR 'Universal Infant Free School Meals' (UIFSM) to enable the proposed works at Thorner C/E Primary School; and
* note that the Asset Management Planning Manager (Built Environment Team) is responsible for scheme delivery which will be completed by October 2016.