Issue - decisions

Changing the Workplace – CtW St George House- Strip Out

13/05/2016 - Changing the Workplace – CtW St George House- Strip Out

The Deputy Chief Executive is requested to give Authority to Spend of £132,468 from existing budget provision (Capital Scheme no. 16256) to enable the completion of the required strip out works in St George House. This will enable the planned refurbishment works (which will be subject to separate approval following detailed design) to be completed in time to enable ‘ leased-in’ premises to be vacated on programme.