41, Allerton Grange Vale - Consent for new culvert

19/05/2016 - 41, Allerton Grange Vale - Consent for new culvert

The Head of Transportation:
i) Granted consent under Section 23 of the Land Drainage Act 1991, for the proposed new culvert;
ii) Approves the following conditions, which will be included with any consent:;
a) The works shall be carried out in accordance with the submitted drawings. Any amendments to the approved drawings will be subject to approval by Council’s Flood Risk Management (FRM) section;
b) The works shall not commence until a construction method statement has been submitted to and approved in writing by FRM;
c) The works shall be commenced within 3 years of the date of the approval. Should the works not be commenced within this time frame, the current approval will be deemed to have lapsed.
d) The applicant shall provide 7 days notice to FRM of their intention to commence the works; and
e) As-built, drawings shall be submitted to FRM on completion of the works.