The Chief Officer (Highways and
Transportation):
i) noted the highway works as outlined in Section 3.1 and indicated
on Sanderson Associates drawing number 8098/006 Rev B to be fully
developer funded.
ii) gave authority to negotiate the terms of and enter into a
tripartite agreement with the developer and Wakefield MDC under the
provisions of Sections 24, 278 and Parts V and VII of the Highways
Act 1980 and Section 111 Local Government Act 1972; whereby the
works associated with the development are carried out by the
Developer’s Appointed Contractor and overseen by Wakefield
Council on Leeds City Council’s behalf;
iii) gave authority to implement the works as set out in Section
3.1.