Design & Cost Report for Hovingham Primary School Expansion - Capital Scheme Number: 32450/HOV/000

15/02/2017 - Design & Cost Report for Hovingham Primary School Expansion - Capital Scheme Number: 32450/HOV/000

The Director of Children’s Services agreed to:

·  Approve the Design & Cost Report form these early works, the cost being £335,500 with the appropriate details of the programme, design and cost as set out in the attached report;

·  Approve entering into an Early Works Agreement with Leeds LEP Limited for £335,500;

·  Note a separate DCR for the main works will follow in March 2017; and

·  Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery.