Issue - decisions

Design & Cost Report for Hovingham Primary School Expansion - Main Works. Capital Scheme Number Number: 324850/HOV/000

31/03/2017 - Design & Cost Report for Hovingham Primary School Expansion - Main Works. Capital Scheme Number Number: 324850/HOV/000

The Director of Children’s Services agreed to:

·  Approve the Design & Cost Report for these main construction works, the cost being £4,664,500 with the appropriate details of the programme, scope and cost as set out in the attached report;

·  Note a separate DCR has been submitted and approved for the Early Works totalling £335,500; and

·  Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery.