The Head of Service Learning Systems agreed to:
1. Authorise expenditure of £261,214 from capital scheme number 32450/BGE/STB to enable the installation of additional ancillary accommodation and essential infrastructure enhancements at St. Bartholomew’s C of E Voluntary Controlled Primary School.
2. Authorise acceptance of the tender submitted by the Leeds Local Education Partnership in the sum of £219,318 including all design and development fees.
3. Note the programme dates identified in section 4.0 of this report in relation to the implementation of this decision.
4. Note that the officer responsible for implementation is the Built Environment Principal Development Officer.