Design & Cost Report & Tender Acceptance for the Learning Places 2017 Bulge Cohort - Grimes Dyke Primary School Capital Scheme Number: 32450/BGE/GRI

13/07/2017 - Design & Cost Report & Tender Acceptance for the Learning Places 2017 Bulge Cohort - Grimes Dyke Primary School Capital Scheme Number: 32450/BGE/GRI

The Chief Officer, Learning Improvement agreed to:

1. Authorise expenditure of £109,816 from capital scheme number 32450/BGE/GRI to enable the refurbishment of an existing area within Grimes Dyke primary school to support the delivery of appropriate teaching space and the removal of a hired modular unit supplied by Portakabin.

2. Authorise acceptance of the tender submitted by Neo Property Solution Ltd. for the sum of £45,427. This figure is inclusive of all design fees, development costs and surveys.

3. Note the programme dates identified in section 4.0 of this report in relation to the implementation of this decision. The final delivery date for this scheme is prior to the commencement of term September 2017.

4. Note that the officer responsible for implementation is the Built Environment Principal Development Officer.