Design & Cost Report and Tender Acceptance for Refurbishment works at Luttrell Crescent Children’s Home Capital Scheme Number: 32453/LUT/000

15/01/2018 - Design & Cost Report and Tender Acceptance for Refurbishment works at Luttrell Crescent Children’s Home Capital Scheme Number: 32453/LUT/000

The Head of Service Learning Systems agreed to:

1. Authorise expenditure of £236,820 from capital scheme number 32453/LUT/000 to undertake the proposed refurbishment works at Luttrell Crescent Children’s Home.

2. Authorise acceptance of the tender submitted by Leeds Building Services in the sum of £210,290. This figure is purely the construction work and is exclusive of ancillary costs.

3. Note the programme dates identified in section 4.2 of this report in relation to the implementation of this decision.

4. Note that the officer responsible for implementation is the Built Environment Project Officer.