The Director of Children and Families agreed
to:
- Approve the expenditure of
£3.99m from capital scheme number 32450/IVE/000 for the
construction work associated with the works required at Iveson
Primary School.
- Approve the transfer of £187K
from the Capital Maintenance budget under code 32654/000/000 to
32450/IVE/000.
- Approve the transfer of £100K
from the Health & Safety budget under code 32790/ELE/000 to 32450/IVE/000
- Note that all works will be carried
out in one phase as opposed to two phases.
- Note that a Design and Cost report
for phase 1 was previously approved by the Director of Children
Services under reference D44611 in July 2017. This DCR replaces the
original DCR approved.
- Note that the whole scheme will be
completed by April 2019, however the works needed to create the
space needed for the academic year 2018/19 will be available from
September 2018.
- Note that the Chief Officer,
Projects, Programmes & Procurement Unit (PPPU) is responsible
for scheme delivery.