Design & Cost Report for Hawksworth Wood Primary School Expansion Phase 2 Works

05/04/2018 - Design & Cost Report for Hawksworth Wood Primary School Expansion Phase 2 Works

The Director of Children & Families agreed to:

 

  1. Approve that £930k of funds authorised for spend under the code 32450/HAW/REF as part of Phase 1 be re-allocated to the 32450/HAW/EXP capital code for Phase 2 works.

 

  1. Approve the expenditure of £2,930k from capital scheme number 32450/HAW/EXP for the construction work associated with the phase 2 works at Hawksworth Wood Primary School necessary for the additional intake from September 2018.

 

  1. Note that the received tenders will be evaluated on price only and that prior to going out to tender, approval via email was obtained from the Head of Learning Systems Children and Families.

 

  1. Note that this second DCR is for the main works and follows the DCR approved for phase 1 works in May 2017.

 

  1. Note that a budget of £4.0m was granted at Executive Board in September 2016 and that this includes the capital costs for phase 1 and 2 DCR’s.

 

  1. Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery.