24/01/2017 - S278 Works associated with the development of 325 dwellings at Spofforth Hill, Wetherby Capital Scheme Number: 32644 ref: 44066    For Determination

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from:

Decision:

The Chief Officer (Highways and Transportation):
i) noted the principles of the highway works as outlined in Section 6.2 and shown on Drawing Numbers 7029/020 Rev C and 7029/021 Rev C as shown at Appendix 3 of this report;
ii) gave authority to negotiate the terms of and enter into an agreement with the developer under the provisions of Section 278 of the Highways Act 1980; whereby the works associated with the development are carried out by this Council at the cost of the developer;
iii) gave authority to incur expenditure of £53,000 works costs, excluding any statutory undertakers costs; and £20,000 staff fees to be fully funded by the developer through the S278 Agreement;
iv) requested the City Solicitor to advertise a notice under Section 23 of the Road Traffic Regulation Act 1984 for the implementation of a formal pedestrian crossing on Spofforth Hill; and
v) gave authority to carry out the detailed design, tender and implement the works as set out in Section 6.2.



Wards affected: Wetherby;

Lead officer: Neil Chamberlain


24/01/2017 - UTC General Traffic Signal Equipment Refurbishment 2016/17 Capital Scheme Number: 32541/000/000 ref: 44065    For Determination

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from:

Decision:

The Chief Officer (Highways and Transportation):
i) noted the contents of this report;
ii) approved the proposal at the total cost of £250,000 ( £145,000 to be spent in 2016/17 and £105,000 in 2017/18 ); and
iii) gave authority to incur expenditure of £210,000 works costs and £40,000 staff costs, to be funded from the LTP Transport Policy Capital Programme (100% Government grant funding ).

Wards affected: (All Wards);

Lead officer: Richard Tallant


24/01/2017 - Cherry Row - Formalisation of parking and footway amendments ref: 44062    For Determination

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from:

Decision:

The Chief Officer (Highways and Transportation):
i) noted the contents of this report;
ii) authorised the detailed design and subsequent implementation of a scheme to alter the footway and parking area on Cherry Row in the Burmantofts’ area as shown on drawing TM-7-2643-01-02; and,
iii) requested the City Solicitor to advertise a draft Traffic Regulation Order to introduce various waiting restrictions in the Burmantofts & Richmond Hill Ward relating to this scheme and any other Traffic Regulation Order amendments in the locality, and, if no valid objections are received, to make and seal the Order as advertised; and
iv) approved an injection of £26,000 into the Capital Programme to be fully funded from private developer contributions; and,
v) gave authority to incur expenditure of £26,000 comprising £19,000 works costs, £3,000 legal fees and £4,000 staff fee costs, all to be fully funded from private developer contributions.

Wards affected: Burmantofts and Richmond Hill; City and Hunslet;

Lead officer: James Chadwick


24/01/2017 - S278 Works associated with the development of a Lidl Store at Miami Site, A642 Aberford Road, Garforth Capital Scheme Number: 32613 ref: 44061    For Determination

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from:

Decision:

The Chief Officer (Highways and Transportation):
i) noted the principles of the highway works as outlined in Section 6.2 and shown on Drawing Numbers 1011-SK-010 Rev C and SK-011 Rev A as shown at Appendix 3 of this report;
ii) gave authority to negotiate the terms of and enter into an agreement with the developer under the provisions of Section 278 of the Highways Act 1980; whereby the works associated with the development are carried out by this Council at the cost of the developer;
iii) requested the City Solicitor to advertise Advertise a notice under Section 23 of the Road Traffic Regulation Act 1984 in order to inform the public of the proposed signal controlled pedestrian crossing on Aberford Road, Garforth;
iv) gave authority to incur expenditure of £750,000 works costs and £105,000staff costs to be fully funded by a developer through a Section 278 Agreement;
v) approved the injection of £855,000 into the Capital Programme, fully funded from a Section 278 ‘private developer’ agreement;
vi) gave authority to carry out the detailed design, tender and implement the works as set out in Section 6.2; and
vii) approved in principal the adoption of new highway construction so that it can be added to the Council’s maintenance regime.


Wards affected: Garforth and Swillington;

Lead officer: Neil Chamberlain


24/01/2017 - Approval of Grass Verge Guidance Document ref: 44060    For Determination

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from:

Decision:

The Chief Officer (Highways and Transportation) noted the contents of the report and approved implementation of the document “Guidance on Protecting Grass Verges".

Wards affected: (All Wards);

Lead officer: Andrew Bellamy


26/02/2018 - Amendments to Leader’s Executive Arrangements ref: 44064    For Determination

Decision Maker: Leader of Council

Decision published: 24/01/2017

Effective from: 26/02/2018

Decision:

The Leader has decided to amend her executive arrangements as detailed in the report and appendices attached.

Lead officer: Kate Sadler


24/01/2017 - Proposed Traffic Regulation Order - Various Sites in Calverley Farsley Ward Phase III Capital Scheme Number: 32656 ref: 44063    For Determination

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from: 24/01/2017

Decision:

The Chief Officer (Highways and Transportation):

i) gave approval to undertake the detailed design, advertisement and implementation of a Traffic Regulation Order at a number of locations in the Calverley Farsley Ward, as detailed on drawing numbers TMW8-1-2598-01D, 01E and TMW8-1-2685-01, at a total cost of £10,000;

ii) gave authority to incur expenditure of £10,000 being £7,000 works costs, and £3,000 internal staff fee costs, to be fully funded from Sect 106 receipts (connected to planning permission agreements) earmarked specifically for traffic management within the Ward; and

iii) instructed the City Solicitor to advertise a draft Traffic Regulation Order as shown on drawing Nos TMW8-1-2598-01D, 01E and TMW8-1-2685-01, if no valid objections are received, to make, seal and implement the Order as advertised.

Wards affected: Pudsey;

Lead officer: Alan Robinson


01/02/2017 - North Yorkshire County Council - Civil Engineering Contractors Framework - Authority to Use Contract ref: 44059    

Approval to use the North Yorkshire County Council Civil Engineering and Painting Contract Framework.

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from: 09/02/2017

Decision:

The Chief Officer Highways and Transportation authorised the use of the North Yorkshire County Council Framework Contracts – Civil Engineering Contractors and Painting Contractors which run until the 31st March 2020.

 

Wards affected: (All Wards);

Lead officer: Nicola Martin


01/02/2017 - Yorkshire & Humberside Supply of Coated Materials, Ready Made Concrete and Aggregates - Approval to Tender ref: 44058    

Approval to tender the Yorkshire & Humberside Supply

of Coated Materials, Ready Made Concrete and

Aggregates

Decision Maker: Director of City Development

Decision published: 24/01/2017

Effective from: 09/02/2017

Decision:

The Chief Officer (Highways & Transportation) approved the recommendation to tender and evaluate the Yorkshire & Humberside Supply of Coated Materials, Ready Mixed Concrete and Aggregates which is to start on 1st April 2017 for a four year period.

Wards affected: (All Wards);

Lead officer: Nicola Martin


23/01/2017 - Procuring services to promote apprenticeships to residents from specific vulnerable and hard to reach groups ref: 44057    For Determination

Decision Maker: Director of Children's Services

Decision published: 23/01/2017

Effective from:

Decision:

The Chief Officer Employment and Skills approved the decision to:
* undertake two intermediate value procurements to commission apprenticeship promotion and support activities targeted at residents from vulnerable and hard to reach groups (BME young people and people affected by autism);
* approve the evaluation criteria in accordance with Contract Procedure Rule (CPR) 15.1 which requires "evaluation criteria to be pre-determined and approved by the relevant Chief Officer" and, the waiver of Contract Procedure Rule 15.2 to permit evaluation on quality only; and
* allocate funding of £30,000 and £25,000 respectiveley from the Apprenticeship Hub budget to these commissions.

Wards affected: (All Wards);

Lead officer: Matt Wilton


30/01/2017 - Passenger Transport, Driver re-grade ref: 44056    Recommendations Approved

The Deputy Chief Executive is requested to authorise the re-grade of the Passenger Transport drivers.

Decision Maker: Deputy Chief Executive

Decision published: 20/01/2017

Effective from: 07/02/2017

Decision:

The Chief Officer (Civic Enterprise Leeds) approved the re-grading of Passenger Transport drivers from A grade to B1 (spinal column point 13) with effect from 1st April 2016

Wards affected: (All Wards);

Lead officer: Julie Hatton


27/01/2017 - Extension of existing Leeds Skyline HIV/AIDS Social Care and Prevention Service Contract from 1 April 2017 for up to 12 months. ref: 44053    

Extension of existing Leeds Skyline HIV/AIDS Social Care and Prevention Service Contract from 1 April 2017 for up to 12 months.

Decision Maker: Director of Adult Social Services

Decision published: 19/01/2017

Effective from: 04/02/2017

Decision:

The Director of Adult Social Services approved the recommendation to waive Contract Procedure Rules (CPRs) 9.1 and 9.2 using the authority set out in CPR 1.3 to enter into a contract for up to one year from 1 April 2017 with Black Health Agency for the provision of Leeds Skyline a HIV/AIDS social care support service. The contract value for 2017/18 will be up to £293,455 (this is made up of £261,455 from Public Health and £32,000 from ASC for rental costs).

 

- The new contract commencing 1 April 2017 will ensure that there is continuity of service while a competitive tendering exercise is carried out.

 

- The Director of Adult Social Services should note that:

 

The Council’s Projects, Programmes and Procurement Unit will be requested to issue the new contract.

 

Sinéad Cregan, Adult Commissioning Manager is the officer responsible for implementation.

Wards affected: (All Wards);

Lead officer: Mick Ward


18/01/2017 - Approval to extend the contract YORE-9BWK7H Supply of Motor Vehicle Spare Parts from 01/02/17 to 31/01/18 ref: 44051    For Determination

Decision Maker: Deputy Chief Executive

Decision published: 18/01/2017

Effective from:

Decision:

The Chief Officer Civic Enterprise Leeds authorised the extension of the contract YORE-9BWK7H Supply of Motor Vehicle Spare Parts for a 12 month period from 01/02/17 to 31/01/18

Wards affected: (All Wards);

Lead officer: Terry Pycroft


18/01/2017 - To commission The Performance Coach to co-facilitate training sessions specialist training sessions on health coaching ref: 44052    For Determination

Decision Maker: Director of Public Health

Decision published: 18/01/2017

Effective from: 18/01/2017

Decision:

The key health and social care providers in Leeds (Public Health Leeds City
Council, Leeds Community Health Care Trust (LCHT) and Leeds and York
Partnership Foundation Trust (LYPFT)) have been working together with Health
Education England (HEE) to develop health coaching as an approach to
improve self-care and management within the health and care system in Leeds.
To help embed health coaching within the Leeds health and care system, NHS
England (NHSE) have provided additional funding for The Performance Coach
to co-deliver 3 training sessions (6 days in total) and enable the Leeds Health
Coaching lnnovation Lead to become competent and accredited to deliver
health coaching training.
The request to waiver CPRs is required as TPC are the only provider of the
European Mentoring and Coaching Council (EMCC) accredited Train the
Trainer Health Coaching course. An accredited course is essential as it
provides an internationally recognised bench mark of competency for this whole
system approach to health coaching. The total cost of this training is [20,870
and it involves 3 training sessions (6 days in total) and quality assurance.
The training will take place between Januarys to March 2017.

Wards affected: (All Wards);

Lead officer: Lucy Jackson


16/01/2017 - Request to enter into a short-term Framework Contract for Special Educational Needs (SEN) School and Collage Placements for a period of 3 months by waiving Contract Procedure Rule (CPR) 9 ref: 44050    For Determination

Decision Maker: Director of Children's Services

Decision published: 16/01/2017

Effective from:

Decision:

The Deputy Director, Safeguarding, Specialist & Targeted Services approved the short-term framework agreement contract for the provision of Special Educational Needs (SEN) School and Collage Placements for children to the providers identified at appendix 1 to the attached report for a period of 3 months.

Wards affected: Various;

Lead officer: Iain Dunn


13/01/2017 - Annual Procurement of Pupil Level Data Sets ref: 44049    For Determination

Decision Maker: Director of Children's Services

Decision published: 13/01/2017

Effective from:

Decision:

The Chief Officer, Partnership Development & Business Support approved the waiver of the following Contracts Procedure Rule No 9.1 and 9.2 and award a contract to Alkemygold Limited in the sum of £14,474.86 (estimate), FFT for the full sum of £50,275 and NCER for the sum of £22,008.96. Contracts are reviewed annually and are in place for a financial year at a time. Alkemygold Limited runs from 1 August to 31 March, or to the completion of services.

Wards affected: (All Wards);

Lead officer: Becky Lawrence


13/01/2017 - Housing ICT Solutions ref: 44048    For Determination

Decision Maker: Director of Environment and Housing

Decision published: 13/01/2017

Effective from:

Decision:

The Director of Environment and Housing approved the award of a contract to Civica UK Limited for the supply of a new suite of housing ICT solutions, for the period 30th January 2017 to 29th January 2024 (7 years) and with the option to extend by a further 3 periods of 12 months (3 years). The Tendered Sum is £2,316,664 which includes initial implementation costs and ongoing maintenance cover over the initial period of 7 years. For the avoidance of doubt, this total excludes third party costs and Leeds City Council Costs of Ownership (hardware and associated support) which were included in the price submission to ensure evaluation was carried out on a like for like basis.

Appendices A, B and C contain exempt information under the Access to Information Rule 10.4 (3). It contains commercially sensitive information including details of tenderers’ submissions and the Council’s evaluation of such submissions, where the public interest in maintaining the exemption outweighs the public interest in disclosing the information.

Wards affected: (All Wards);

Lead officer: Richard Ellis


13/01/2017 - Approval to award contracts to Oracle Corporation Ltd for the provision of Technical Support Services on an annual renewal basis for a period of up to 5 years using the Negotiated Procedure without prior publication of a contract notice. ref: 44045    For Determination

Decision Maker: Deputy Chief Executive

Decision published: 13/01/2017

Effective from:

Decision:

Award of contracts to Oracle Corporation Ltd for the provision of Technical Support Services on an annual renewal basis for a period of up to 5 years using the Negotiated Procedure without prior publication of a contract notice.

Wards affected: (All Wards);

Lead officer: Stephanie Dunn


23/01/2017 - Request to extend White Rose Children's 16+ Accommodation and Support for Care Leavers and Vulnerable Young People Regional Framework for a period of 11 months ref: 44047    

To extend the current contract for a period of 12 months, from the period of 18th December 2016 – 18th December 2017.

Decision Maker: Director of Children's Services

Decision published: 13/01/2017

Effective from: 31/01/2017

Decision:

The Director of Children’s Services approved the extension of the White Rose Children’s 16+ Accommodation and Support for Care Leavers and Vulnerable Young People Regional Framework for a period of 11 months to the providers listed at appendix 1 to the attached report.

Wards affected: (All Wards);

Lead officer: Iain Dunn


23/01/2017 - Shakespeare Primary School Expansion - Design and Cost Report ref: 44046    

Request for authority to spend to create 315 additional pupil places through the expansion and relocation of Shakespeare Primary School.

The decision is a Key Decision because it will be greater than £250k.

 

Decision Maker: Director of Children's Services

Decision published: 13/01/2017

Effective from: 31/01/2017

Decision:

The Director of Children’s Services agreed to:

 

·  Approve the design and cost report for the scheme to expand and relocate Shakespeare Primary School, the cost being £11,585,080 with the appropriate details of the programme, design and cost report as set out in this report; and

 

·  Note that the Chief Officer, Projects, Programmes and Procurement Unit id responsible for scheme delivery which is scheduled for completion by September 2018.

Wards affected: Burmantofts and Richmond Hill; Gipton and Harehills;

Lead officer: Jacqueline Robertson


12/01/2017 - Head Start Phase 2 Programme ref: 44044    For Determination

Decision Maker: Director of Children's Services

Decision published: 12/01/2017

Effective from:

Decision:

The Chief Officer Emplyment and Skills waived Contract Procedure Rule (CPR) 21.7 to allow the vatiation of an existing contract, that will increase the participant numbers on the Head Start Phase 2 Programme from 45 to 50 and, waived Contract Procedure Rule (CPR) 7.1 to increase the total maximum value of the Aspire IGEN contract by £9,250, which is low value contract under £10,000 and represents best value for money.

Wards affected: (All Wards);

Lead officer: Michelle Anderson


12/01/2017 - Appointment of Specialist Adult Learning Provider ref: 44043    For Determination

Decision Maker: Director of Children's Services

Decision published: 12/01/2017

Effective from:

Decision:

The Chief Officer Employment & Skills approved the award of a low value contract in accordance with Contract Procedure Rules (CPR) 7 and, the invocation of CPR 7.1 to appoint J2Profit to undertake a destination survey of learners on the Council's Adult Learning Programme. And authorised expenditure not exceeding £10,000 to J2Profit to carry out this work. The costs to be fully met from the Council's externally funded Adult Education Budget.

Wards affected: (All Wards);

Lead officer: Michelle Anderson


12/01/2017 - Amendments to Leader’s Executive Arrangements ref: 44042    For Determination

Decision Maker: Leader of Council

Decision published: 12/01/2017

Effective from:

Decision:

The Leader has decided to amend her executive arrangements as detailed in the report and appendices attached. With effect from 4th January 2017

Lead officer: Kate Sadler


11/01/2017 - Record of Decisions - Child Performance Licences, Child Chaperone Licences and Children's Work Permits - November 2016 ref: 44041    For Determination

Decision Maker: Director of Children's Services

Decision published: 11/01/2017

Effective from:

Decision:

The Area Head of Targeted Services (ENE) agreed to publish the attached record of decisions made in November 2016.

Wards affected: Various;

Lead officer: Ruth Kitson


11/01/2017 - Record of Decisions - Child Performance Licences, Child Chaperone Licences and Children's Work Permits - October 2016 ref: 44040    For Determination

Decision Maker: Director of Children's Services

Decision published: 11/01/2017

Effective from:

Decision:

The Area Head of Targeted Services (ENE) agreed to publish the attached record of decisions made in October 2016.

Wards affected: Various;

Lead officer: Ruth Kitson


18/01/2017 - Seek approval to procure materials provider for the provision of Class 1 materials (boilers, radiators, control panels) for domestic gas contracts) ref: 44038    

Report to seek approval to procure materials provider for the provision of Class 1 materials for domestic gas contracts

 

 

 

Decision Maker: Director of Environment and Housing

Decision published: 10/01/2017

Effective from: 26/01/2017

Decision:

The Director of Environment and Housing agreed to grant the authority to spend circa £5.6m over the initial 2 year contract term. To approve the proposed direct call off from Fusion 21 and award a contract to Jewson Limited - Trading as Graham for a period of 2 years with the option to extend for a further 2 x 12  months.

 

Wards affected: (All Wards);

Lead officer: David Gold


18/01/2017 - Design & Cost Report for Park Spring Primary School Expansion, Capital Scheme Number: 32450/PAR/000 ref: 44039    

Request for the Authority to Spend to provide permanent accommodation to facilitate the expansion of Park Spring Primary School from a capacity of 315 pupils to 420.

Decision Maker: Director of Children's Services

Decision published: 10/01/2017

Effective from: 26/01/2017

Decision:

The Director of Children’s Services agreed to:

 

  i.  Approve the Design and Cost Report for the second phase of enabling works to provide temporary hard play to facilitate the main scheme at Park Spring Primary School, the cost being £280k, with the appropriate details of the programme, design and cost as set out in this report.

 

  ii.  Approve entering into an Early Works Agreement with Clugston Construction Limited for £280k.

 

  iii.  Note that Authority to Spend was approved for capital of £278k and revenue of £157k on 14/06/16 for enabling works (temporary accommodation) to facilitate the permanent expansion.

 

  iv.  Note a separate DCR for the main works will follow in late January 2017.

 

  v.  Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery.

Wards affected: Pudsey;

Lead officer: David O'Connor


12/01/2017 - West Yorkshire Combined Authority Framework Contracts - Specialist Professional Services, Professional Services and Asset Delivery - Authority to Use ref: 44030    

Approval to use the Framework Contracts prepared by the West Yorkshire Combined Authority.

Decision Maker: Director of City Development

Decision published: 04/01/2017

Effective from: 20/01/2017

Decision:

The Chief Officer Highways and Transportation authorised the use of the West Yorkshire Combined Authority Specialist Professional Services, Professional Services and Asset Delivery Contracts.

 

Wards affected: (All Wards);

Lead officer: Andrew Wheeler