To approve the replacement of the existing roundabout with a signalised gyratory and associated pedestrian, cycling and public transport improvements.
To approve the implementation of the scheme and to give authority to incur expenditure of £3,475,000: comprising £2,432,000 DfT Pinch Point funding; £731,761 developer funding and £311,239 from the LTP 2014/15
Decision type: Key
Reason Key: Expenditure > £250,000;
Decision status: Recommendations Approved (subject to call-in)
Wards affected: Calverley and Farsley;
Notice of proposed decision first published: 13/02/2014
Decision due: 2 Apr 2014 by Executive Board
Lead director: Director of City Development
Department: City Development
Contact: Paul Russell, Principal Engineer 0113 2476171 Email: paul.russell@leeds.gov.uk.
Consultation process
Email and letter drop
Consultees
Executive Member for Development and the Economy
Ward Members
Residents
Businesses
Emergency Services
Metro
Portfolio Holder: Development and the Economy