a) Authorise programme expenditure and authority to spend from capital scheme number 16585/ASQ/000 to build the Asquith Primary School extension.
b) Note the programme dates identified in this report in relation to the implementation of this decision.
c) Note that officer responsible for implementation is the Project Manager, PPPU.
Decision type: Key
Reason Key: Expenditure > £250,000;
Decision status: Recommendations Approved
Wards affected: Morley North;
Notice of proposed decision first published: 03/04/2014
Decision due: 25 Jun 2014 by Executive Board
Lead director: Director of Children's Services
Department: Children's Services
Contact: Nigel Wilson, Senior Contract Manager 07891 275570 Email: nigel.wilson@leeds.gov.uk.
Consultees
Executive Board - April 2014
Public Consultation – December 2013
Member briefing at key project stages