· Approve an injection of capital of £3.1 m to invest in a 2MW peak gas- fired electricity generating station with heat recovery that will be incorporated into the base specification for the Merion House refurbishment project;
· Authorise the Deputy Chief Executive to take any necessary further action to facilitate the installation of the generation station.
Decision type: Key
Reason Key: Expenditure > £250,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 23/03/2015
Decision due: 22 Apr 2015 by Executive Board
Lead director: Deputy Chief Executive
Department: Resources
Contact: Peter Lynes, Group Manager- Energy and Water 0113 2475539 Email: peter.lynes@leeds.gov.uk.
Consultation process
|
|
|
|
|
Consultees
Service area of the Council plus a senior union representative for
communication, consultation and engagement purposes. These
representatives have also co-ordinated the information from their
service areas for planning purposes.
briefed and consulted on the proposals where appropriate,.
Senior Members are updated on the whole Merrion House refurbishment Project on a regular basis on progress. |
Regular key stakeholders meetings are held with Chief Officers from each |
The Corporate Leadership Team and Senior Management Teams have been |
Portfolio Holder: Councillor Gruen