Issue details

Bridgewater Place Settlement Agreement

To agree the terms of the settlement agreement relating to the expenditure that has been incurred by LCC in providing temporary mitigation measures to safeguard highway users from the impact of the wind generated nuisance caused by the Bridgewater Place Building pending the introduction of permanent measures by the Building Owner.

Decision type: Key

Reason Key: Affects more than 1 ward;

Decision status:

Wards affected: City and Hunslet;

Notice of proposed decision first published: 27/11/2015

Decision due: Not before 4th Jan 2016 by Director of City Development

Lead director: Director of City Development

Department: City Development

Contact: Nicola Murphy, Section Head - Civil Litigation Email: nicola.murphy@leeds.gov.uk.

Consultation process

Briefings

Consultees

Executive Member for Regeneration, Transport and Planning