Issue details

Design & Cost Report for Greenside Primary School Expansion

Request for the Authority to Spend to expand Greenside Primary School from a capacity of 315 pupils to 420 pupils by increasing the admission number into reception from 45 pupils to 60 pupils with effect from 1st September 2017.

Decision type: Key

Reason Key: Expenditure > £250,000;

Decision status:

Wards affected: Pudsey;

Notice of proposed decision first published: 07/04/2017

Decision due: Not before 8th May 2017 by Director of Children and Families

Lead director: Director of Children and Families

Department: Children and Families

Contact: David O'Connor, Project Manager 07891 278355 Email: david.oconnor@leeds.gov.uk.

Consultation process

Public consultation provisionally planned to take place between June and July 2017.

Consultees

School, early year providers, public and elected members.

Decisions