Issue details

Design & Cost Report for Hawksworth Wood Primary School Expansion Phase 2 Works

Request for the authority to spend to create an additional 120 places through the expansion of Hawksworth Wood Primary School under the Learning Places Programme.

Decision type: Key

Reason Key: Expenditure > £250,000;

Decision status:

Wards affected: (All Wards);

Notice of proposed decision first published: 15/03/2018

Decision due: Not before 13th Apr 2018 by Director of Children and Families

Lead director: Director of Children and Families

Department: Children and Families

Contact: Imtiaz Hasan, Project Manager 07891 277112 Email: Imtiaz.hasan@leeds.gov.uk.

Consultation process

The proposal to expand the school was subject to a statutory process issued on September 2016 including public consultation. The expansion of the school was subsequently approved by Executive Board in December 2016. 

Public consultation at the school was held on the 14th June 2017 where representatives from Panning, Highways, PPPU and NPS were in attendance to discuss the proposals.

Consultees

Consultation with key stakeholders including members of school and the children centre leadership team, the governing body, officers from Children and Families, ward members has been carried throughout the design process and will continue throughout the construction stage.

Decisions