Purpose:
To approve the implementation of the scheme and to give authority to incur expenditure of £500,000 funded from Highways Annual Capital Programme.
Decision:
The Chief Officer (Highways and Transportation):
i) noted the contents of this report;
ii) noted the highway works as outlined in Section 3 and indicated on Drawing Number 299649-LCC-HWT-PH2-DR-CH-MI_02_ shown as Appendix 1 of this report;
iii) gave authority to complete the detailed design, and implement the works as set out in Section 3 using Highway Maintenance Seacroft Depot as Contractor; and
iv) gave authority to incur expenditure of £450,000 works costs and £50,000 staff fees to be funded from LCC capital borrowing resources.
Reason Key: Expenditure > £250,000;
Wards Affected: Chapel Allerton;
Other reasons / organisations consulted
Via email and letter drop
Consultees
Ward Members
Residents
Local Residents Group
Contact: Richard Stewart, Highways Officer 0113 378 7386 Email: richard.stewart@leeds.gov.uk.
Publication date: 06/06/2018
Date of decision: 14/06/2018
Effective from: 22/06/2018