Reference: D47653
Decision Maker: Director of City Development
Is Key decision?: Yes
Is subject to call in?: Yes
Authority to spend from existing budget provision (scheme 16996) on maintenance works to Leeds Town Hall.
The Director City of Development:
i) Approved expenditure from existing budgetary provision, Capital Scheme No 16996, for maintenance work to the roofs at Leeds Town Hall;
ii) Approved the appointment of Interserve Construction Ltd as the main contractor to carry out the works to the roofs at Leeds Town Hall, subject to the provisions contained in confidential appendix 3 of the Design and Cost Report being in place;
iii) Noted the contract value with Interserve Construction Limited will be £4,133,200.
Reason Key: Expenditure > £250,000;
Other reasons / organisations consulted
Emails, meetings
Consultees
Executive Member and Ward Members
Contact: Martin Gresswell 0113 3787742.
Publication date: 13/06/2018
Date of decision: 21/06/2018
Effective from: 29/06/2018
Accompanying Documents: