i) noted the contents of the report;
ii) approved the detailed design and implementation of a package of
highway works associated with the expansion of Hunslet Moor Primary
school, as shown on the attached Drawing No
1072603-WSP-HWT-HMS-DR-CH-0001, at a total cost of
£10,000;
iii) noted the required expenditure of £10,000, comprising
£5,500 works costs, £3,500 staff fees and £1,000
legal fees, all being funded from the Children’s Services
Learning Places Capital Programme ( previously approved );
iv) gave authority to advertise and introduce a Traffic Regulation
Order to introduce waiting restrictions as shown on Drawing No
1072603-WSP-HWT-HMS-DR-CH-0001; and
v) authorised the City Solicitor to advertise a draft Traffic
Regulation Order and if no valid objections are received, to make,
seal and implement the Order as advertised
Wards Affected: Hunslet and Riverside;
Contact: Nick Borras, Senior Engineer - Traffic Management 0113 3787497 Email: nick.borras@leeds.gov.uk.