Reference: D48612
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways &
Transportation);
(i) noted the Executive Board approval on 25th July 2018 to
progress Package 5a to detail design and construction;
(ii) noted that the LPTIP Bus Infrastructure Package Board was
informed of the current design of Package 5a in October 2018;
(iii) noted that WYCA approved the Outline Business Case for the
A647 Bus Priority Corridor project in February 2019;
(iv) noted that in February 2019, Executive Board gave approval for
detail design and construction of the A647 Bradford to Leeds Bus
Priority Corridor to be carried out, including Package 5a;
(v) approved the preliminary design of Package 5a – A647
Gloucester Terrace; and
vi) approved the commencement of detail design of Package 5a
– A647 Gloucester Terrace.
Wards Affected: (All Wards);
Contact: Morgan Tatchell-Evans, Highways Officer 0113 378 3655 Email: morgan.tatchellevans@leeds.gov.uk.
Publication date: 18/04/2019
Accompanying Documents: