The Director of Resources & Housing:
a) approved the award of the contract for the Apex Data Centre CRAC
Unit Replacement Project to Keysource Limited for the sum of
£412,257.04
b) noted that it is estimated the works will take approximately 8
months to complete from 1st July 2020, as outlined in 3.11 of the
report.
Wards Affected: (All Wards);
Contact: Adam Edmands, Data Centre & Voice Team Manager 0113 37 84303 Email: Adam.Edmands@leeds.gov.uk.
Publication date: 23/06/2020