Decision details

Award of an interim maintenance contract for Merrion House gas-fired generators

Reference: D52634

Decision Maker: Director of Resources

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Chief Officer (Sustainable Energy & Air Quality):
a) Approved the waiver of Contracts Procedure Rules 8.1 and 8.2 (relating to the requirement for competition for intermediate value procurements) in respect of an interim maintenance contract for the Merrion House gas-fired generators;
b) Approved the award of a contract to Edina UK Ltd in the sum of £90k for the maintenance of the Merrion House gas-fired generators, with the contract intended to commence on 5th January 2021 and expire on 4th January 2022.

Contact: Andrew Lingham 0113 3786370 Email: andrew.lingham@leeds.uk.gov.

Publication date: 05/01/2021