Reference: D52642
Decision Maker: Director of Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Director of Resources & Housing:
• Agreed to waive CPR 3.1.5 as the proposed procurement
approach represents a deviation from the established process of
using the YORbuild2 framework.
• Noted that the Head of Council Housing Growth, as per the
scheme of delegation, has approved an initial feasibility study of
a potential new housing scheme at Healey Croft, Tingley, Leeds and
the costs incurred through the feasibility stage for surveys and
third party consultancy costs of £155k;
• Noted that Head of Asset Management has approved the
allocation of the Healey Croft Site for the use of the council
housing growth programme under his delegated authority through the
Director of City Development;
• Approved the appointment of Wilmott Dixon Construction
Limited via direct call off from the Scape Framework (Major Works)
to complete the feasibility and the award of a Pre-Construction
Services Design Agreement (PCSDA) at a cost of £282,911
excluding VAT to complete the detailed design development and cost
estimating prior to contract award.
• Noted that a further report will follow to seek Director
Approval to award an NEC Construction contract for the scheme,
subject to a successful outcome to the planning process.
Wards Affected: Ardsley and Robin Hood;
Contact: Mark Denton 07891 278062 Email: mark.denton@leeds.gov.uk.
Publication date: 11/01/2021