Reference: D54296
Decision Maker: Director of City Development
Is Key decision?: Yes
Is subject to call in?: Yes
Approval to award construction contract to deliver new council housing at Healy Croft, Tingley
The Director of City Development has authorised:
a. Expenditure of £3,280,518 from capital scheme 33103/HEA to deliver 9
homes at Healy Croft, Tingley.
b. Entering into an NEC3 Engineering and Construction Contract (NEC3
ECC) Option A with Willmott Dixon Construction Ltd for the delivery of 9 new
council homes at Healy Croft, Tingley for the sum of £2,586,115.13 (included
within the £3,280,518 as included at recommendation a); enabling a contract
start date of 2nd August 2021, a site access date of 2nd August 2021 and a
completion date of 6th June 2022;
c. Vary the current Delivery Agreement with Perfect Circle for on site
management services of the Healy Croft contract for the sum of £215,570.97
throughout RIBA stage 5-7.
Reason Key: Financial Impact>£500K;
Wards Affected: Ardsley and Robin Hood;
Other reasons / organisations consulted
Briefings with Local Ward Members
Consultees
Briefings with Local Ward Members
Contact: Laura Whitehead 0113 378 5910 Email: Laura.Whitehead@leeds.gov.uk.
Publication date: 09/07/2021
Date of decision: 19/07/2021
Effective from: 27/07/2021