Reference: D55293
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
a) Noted the detail of the highway works provided in paragraph 4 of
this report and as shown on the plan included at Appendix 3 of this
report;
b) Gave authority to negotiate the terms of and enter into an
agreement with the developers under the provisions of Section 278
of the Highways Act 1980; whereby the works associated with the
development are carried out by the developers under Leeds City
Council’s supervision;
c) Gave authority to request the City Solicitor to advertise a
draft Traffic Regulation Order (TRO) to provide ‘No Waiting
At Any Time’ restrictions and 20mph order as shown on the
plan included at Appendix 3 of this report; and if no valid
objections are received, to make seal and implement the Orders as
advertised;
d) Approved the adoption of new highway construction on land
hatched in red on drawing number 1372/02/02.01/J so that it can be
added to the Council’s maintenance regime; and
e) Gave authority to incur capital expenditure of £20,000,
consisting of £10,000 legal costs and £ 10,000 staff
costs, all to be fully rechargeable to the developer through the
Minor Section 278 agreement. These are subject to estimated
coststhrough the Section 278 agreement. These are subject to
contractor estimated costs.
Wards Affected: Bramley and Stanningley; Calverley and Farsley;
Contact: Gordon Maclay, Travel Planning Co-ordinator 0113 33 88090 Email: gordon.maclay@leeds.gov.uk.
Publication date: 19/05/2022
Accompanying Documents: