Reference: D55652
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation);
a) Noted the detail of the highway works provided in paragraph 3 of
this report and as shown on GA drawing
733531-LCC-HWT-XX-DR-CH-GA_001 PO5 included at Appendix 3 of this
report;
b) gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by Leeds City Council, fully funded by
the developer;
c) gave authority to incur capital expenditure of £565,000
works costs, £96,000 staff fees, £32,000 upgrade of
speed camera at Victoria Road, and £1,093 undertaking
‘before and after’ noise measurements, to be fully
funded by the developer through the S278 Agreement;
d) gave authority to adopt the land associated with the highway
works shown on drawing 733531-LCC-HWT-XX-DR-CH-GA_001 PO5 Appendix
3 so that it can be added to the Council’s maintenance
regime; and
e) gave authority to complete the detailed design, tender and
implement the works as provided for within the Section 278
Agreement and as outlined in paragraph 2 of this report.
Wards Affected: Morley North;
Contact: Catherine Kimuli, Highways Officer 0113 3788089 Email: catherine.kimuli@leeds.gov.uk.
Publication date: 26/09/2022
Accompanying Documents: