Decision details

Design & Cost Report for Hunslet St Mary's Primary School Learning Places Project & Application to Access Capital Fund Contingency. Capital Scheme Number: 32450/HSM/000

Reference: D44537

Decision Maker: Director of Children's Services

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Request for authority to spend to create 105 additional pupil places through the expansion of Hunslet St Mary’s CofE Primary School.

Decision:

The Director of Children and Families agreed to:

 

  1. Approve the design and cost report for the scheme at Hunslet St Mary’s Primary School, the cost being £1,827,754 with the appropriate details of the programme, design and cost as set out in this report; and

 

  1. Approve the application to access the Capital Risk Fund for an additional £227,754 in line with this report

 

  1. Approve the award of the works to the ISP in the total sum of £1,394,051.27, Leeds Building Services in line with CPR 3.1.5

 

  1. Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery which is scheduled for completion by 4th December 2017.

 

Reason Key: Expenditure > £250,000;

Wards Affected: City and Hunslet;

Other reasons / organisations consulted

Ward members consulted by email and briefing on 13 December 2016. Public Consultation for planning on 16 January 2017. Further consultation throughout the project.

Consultees

Ward members, school, governors, parents and residents.

Contact: Adele Berry, Project Assistant PPPU 07891 275964 Email: adele.berry@leeds.gov.uk.

Publication date: 27/06/2017

Date of decision: 05/07/2017

Effective from: 13/07/2017