Decision details

Heritage Maintenance Programme Phase 1 - Yeadon Town Hall

Reference: D50177

Decision Maker: Director of City Development

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval to carry out Phase 1 Heritage Maintenance Work at Yeadon Town Hall.

Decision:

The Chief Officer Asset Management and Regeneration:

 

a)  Gave Authority to Spend of £630,320 from existing budgetary provision, Capital Scheme No. 16996, for maintenance work to Yeadon Town Hall.

b)  Approved the appointment of Stone Edge Ltd. as the main contractor to carry out the proposed works to Yeadon Town Hall.

c)  Noted the contract value with Stone Edge Ltd. will be £430,210.

 

Wards Affected: Otley and Yeadon;

Other reasons / organisations consulted

Ward Member briefing notes

Consultees

Relevant Ward Members

Contact: Malcolm Fisher 07891 274515 Email: malcolm.fisher@leeds.gov.uk.

Publication date: 02/10/2019

Date of decision: 10/10/2019

Effective from: 18/10/2019

Accompanying Documents: