Reference: D50516
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation);
i) noted the principles of the highway works to provide safe
pedestrian and vehicular access to the development site;
ii) gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by the developer and overseen by the
Council;
iii) gave authority to incur expenditure of £7,500 TRO costs
and £5,000 staff checking and inspection costs, all to be
fully rechargeable to the developer through the Section 278
agreement;
iv) approved the adoption of new highway construction on land
shaded yellow on drawing number P-18-00247-Met-M2-C-006 Rev 6 shown
at Appendix 4 of this report so that it can be added to the
Council’s maintenance regime; and
v) requested the City Solicitor to advertise a draft Traffic
Regulation Order to introduce Time Limited Waiting and Loading
restrictions in the new lay-bys along the Burley Street and Park
Lane site frontages and the prohibition of motor vehicles on
Rutland Mount as shown on drawing S278/RM/TRO-01 shown at Appendix
5; and if no valid objections are received, to make and seal the
TRO as advertised.
Wards Affected: Little London and Woodhouse;
Contact: Michael Norcliffe, Highways Officer 0113 3788092 Email: michael.norcliffe@leeds.gov.uk.
Publication date: 05/02/2020