The Chief Officer (Highways and
Transportation):
i) noted the contents of this Report;
ii) approved the detailed design and subsequent installation of the
proposed scheme as noted on drawing TE-17-519-GA; and
iii) gave approval to spend £10,000 on this scheme, being
£2,500 staff fees and £7,500 works costs, to be funded
by the LTP Transport Policy Capital Programme (100% Government
grant funding).
Wards Affected: Horsforth;
Contact: Jonathan Waters, Highways Officer 0113 3787492 Email: jonathan.waters@leeds.gov.uk.
Publication date: 25/06/2020