Local Centres Programme – Chapel Allerton Centre
Reference: D52314
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
The Chief Officer (Highways and
Transportation);
i) approved the detailed design of a package of measures in the
centre of Chapel Allerton, as outlined in drawing TM/09/2402/12/02d
and give authority to implement the works;
ii) noted the required expenditure of £190,000, comprising
£170,000 works costs, £19,000 staff fees and
£1,000 legal fees, with £150,000 being funded from the
Regeneration Local Centres Capital Programme and £40,000 from
Highways Traffic Management Section 106 contributions;
iii) gave approval to inject £40,000 into the Capital
Programme funded from Highways Traffic Management Section 106
contributions;
iv) gave authority to spend £40,000 funded from Highways
Traffic Management Section 106 contributions; and
v) authorised the City Solicitor to advertise a notice under the
provisions of Section 90c of the Highways Act 1980 and advertise
draft Traffic Regulation and Movement Orders and if no valid
objections are received, to make, seal and implement the Traffic
Regulation and Movement Orders as advertised.
Wards Affected: Chapel Allerton;
Contact: Nick Borras, Senior Engineer - Traffic Management 0113 3787497 Email: nick.borras@leeds.gov.uk.
Publication date: 25/09/2020