Reference: D52524
Decision Maker: Director of Children and Families
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Director of Childrens & Families
agreed to:
a) Set the overall project budget for the development of the East
Leeds Free School at £30m and provide ‘approval to
spend’ on £22.63m, noting that £7.37m has been
previously approved under the ‘early works’ programme.
Draw down of the budget will be subject to future design cost
reports and approvals at the appropriate juncture.
b) Note, the full scheme budget figure of £30m is inclusive
of all aspects of the project with the exception of the required
off-site Highways works and land purchase. It includes; the
construction contract figure, client held contingency, furniture
and equipment, service connections etc.
c) Note, provisional ‘approval to spend’ was granted at
the September 2019 Executive Board and identified a budget between
£25m and £30m, which was subject to development of the
scheme.
d) Note the programme dates identified in section 3.2 of this
report, in relation to the implementation of this decision,
represents the critical path for project success and must be
adhered to where possible.
e) Note that the officer responsible for implementation is the Head
of Service Learning Systems.