Decision details
Section 278 Highway Works - Bodington Avenue, Adel, Leeds
Reference: D54889
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
The Chief Officer (Highways and
Transportation) has:
a) Noted the detail of the highway works as set out in paragraphs
1-7 in the Design and Cost report and as shown on the plan included
at Appendix 3;
b) Given authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by Leeds City Council at the cost of
the developer;
c) Given authority to request the City Solicitor to advertise a
draft Traffic Regulation Order (TRO) to provide ‘No Waiting
At Any Time’ restrictions in the vicinity of the proposed
access as shown on the plan included at Appendix 3; and if no valid
objections are received, to make seal and implement the Orders as
advertised; and
d) Given authority to incur capital expenditure of £550,000,
consisting of £453,333.00 works costs and £ 96,667.00
staff costs, all to be fully rechargeable to the developer through
the Section 278 agreement. These are subject to contractor
estimated costs.
Wards Affected: Adel and Wharfedale;
Contact: Ahmad Huneidi, Senior Engineer 0113 336 8651 Email: Ahmad.Huneidi@leeds.gov.uk.
Publication date: 18/01/2022