Design & Cost Report for S278 Highway Works Associated with planning permission (ref: 21/06099/FU) for the construction of sixteen rain gardens and associated pipework
Reference: D54891
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
The Chief Officer (Highways and
Transportation):
a) Noted the detail of the highway works described in outline in
paragraph 3 of this report and shown on plan
ROU06-MMB-WTN-NCS-DR-T-1101-C04 attached at Appendix 3; and
b) Gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by the developer and overseen by the
Council.
Wards Affected: Roundhay;
Contact: Gema Garcia, Highways Engineer 0113 37 86412 Email: gema.garcia@leeds.gov.uk.
Publication date: 18/01/2022