Decision details
EV On-Street Residential Charge point Scheme – Bid 2
Reference: D55536
Decision Maker: Director of Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
The Chief Officer of Sustainable Energy &
Air Quality:
1. Approved the receipt of funding from the Office for low Emission
Vehicles and subsequent injection of £202,500 grant funding
into the Early Measures Capital Scheme.
2. Authorised the expenditure of the £202,500 ORCS external
grant funding to cover the work streams itemised above.
3. Authorised expenditure of up to £47,793.16 from the Early
Measures budget to cover capital costs. There is an existing ring
fenced budget for public charge point delivery within this
scheme.
4. Approved the additional investment of £44,169.39 that will
be provided by the charge point operator. This funding will be the
operator’s contribution to the overall costs of the scheme
and will not be received by the authority. This provides a total
expenditure of £294,462.55 for the scheme, of which
?£250,293.16? is from the capital budget secured by SEAQ from
external funding.
5. Approved the award of this work directly to EB Charging Ltd in
line with the reasoning in 3.3 and 3.4 through the approved KCS
framework contract.
Wards Affected: Various;
Contact: James Hulme, James Hulme 0113 3786996.
Publication date: 04/08/2022
Date of decision: 04/08/2022