Pudsey Bus Station Redevelopment

Meeting: 08/10/2008 - Executive Board (Item 103)

103 Pudsey Bus Station - Associated Highway Works pdf icon PDF 2 MB

To consider the report of the Director of City Development on the design and implementation of the associated highway works required to accommodate the redevelopment of Pudsey Bus Station.

 

Additional documents:

Minutes:

The Director of City Development submitted a report on the design and implementation of the associated highway works required to accommodate the redevelopment of Pudsey Bus Station.

(a)  That approval be given to the design and implementation of associated highways works to the redevelopment of Pudsey Bus Station as set out in the submitted report and on drawing HDC/298886/C06, at a total cost of £766,750.

(b)  That authority be given to incur expenditure of £615,000 works and £131,750 staff costs (£20,000 previously approved) which can be met from the Integrated Transport Scheme 99609 within the approved Capital Programme.

(c)  That it be noted that a separate report will be presented to the Chief Highways Officer seeking approval for the advertising and sealing of the associated Traffic Regulation Orders.