87 Sharp Lane Primary School - Creation of New Entrance and Provision of Remodelling Works PDF 44 KB
To consider the report of the Chief Executive of Education Leeds on proposals to create a new entrance and undertake associated remodelling works at Sharp Lane Primary School and to incur the necessary expenditure.
Minutes:
The Chief Executive of Education Leeds submitted a report on proposals to create a new entrance and undertake associated remodelling works at Sharp Lane Primary School and to incur the necessary expenditure.
(a) That the design proposals in respect of the scheme to create a new entrance and undertake associated remodelling works at Sharp Lane Primary School be approved.
(b) That the injection of a Section 106 funding contribution, in the sum of £2,866,204, into the approved Capital Programme be approved
(c) That expenditure of £902,200 be authorised in respect of this scheme.