RHB 2008-11 Programme Beverleys Acquisition and Demolition Scheme

Meeting: 08/10/2008 - Executive Board (Item 110)

110 Update report on the Regeneration of 'The Beverleys' Area of Beeston pdf icon PDF 89 KB

To consider the report of the Director of Environment and Neighbourhoods providing an update on the progress of the Beverleys acquisition and demolition scheme and seeking authority to incur the proposed expenditure to undertake the scheme.  

 

Minutes:

The Director of Environment and Neighbourhoods submitted a report providing an update on the progress of the Beverleys acquisition and demolition scheme and on the proposed expenditure to undertake the scheme.

 

RESOLVED

(a)  That approval be given to the injection of additional private sector resources of £156,000 received from Beeston Group Repair Phase 2 additional to those previously accounted for within this group repair scheme.

(b)  That Scheme Expenditure to the amount of £2,952,700 be authorised .

(c)  That officers report back in future on the progress of the scheme.