Issue - decisions

Lift Replacement programme 2018/19-2020/21:- Year 3 delivery plan

30/10/2019 - Lift Replacement programme 2018/19-2020/21:- Year 3 delivery plan

The Director of Resources and Housing agreed to approve the delivery of the year 3 lift replacement programme by the issue of a task order in early November 2019 to instruct Lifts Engineering Services (LES) via the use of the CHIC (Central Housing Investment Consortia) Term Partnering Contract for Passenger Lifts. This will allow the delivery of an agreed programme of works for lift replacements in year 3 (2020/21) to the sum of £3.2m.