Issue - decisions
Tender Acceptance Report (TAR) for the 60 place bulge at Cockburn Academy from September 2020
17/09/2020 - Tender Acceptance Report (TAR) for the 60 place bulge at Cockburn Academy from September 2020
• Authorisation to proceed with
acceptance of the tender submitted by Leeds D&B One in the sum
of £5,496,346.57 for the phase one works. Leeds D&B One
will then enter into contract with Interserve Construction Ltd for
£2,587,332.57 and Portakabin Ltd for £2,419,400. The
contract sum of £5,496,346.57 also includes LEP fees of
£489,614.
• In line with Leeds City Council’s Contract Procedure
Rule 3.1.5, the requirements are subject to existing exclusive
contract arrangements with Leeds D&B One.
• Note that the officer responsible for implementation is the
Head of Service, Learning Systems and the Head of Programmes and
Projects, City Development and authorise them as a signatory of all
other contract related documentation that is required to deliver
this project.