Issue - decisions
Design & Cost Report for additional works associated with the Learning Places expansion of Carr Manor Community School (Primary Phase)
28/04/2021 - Design & Cost Report for additional works associated with the Learning Places expansion of Carr Manor Community School (Primary Phase)
The Head of Service, Learning Systems agreed
to:
1. Approve the expenditure of £264,245.96 from capital scheme
number 32655/CAR/000 for the remaining works necessary to complete
the Learning Places Expansion of Carr Manor Community School.
2. Note that the original ‘approval to spend’ figure
for the Carr Manor Community School project was £5m, of which
£4,674,243.89 has been drawn down previously.
3. Note that the officer responsible for implementation is the Head
of Service Learning Systems and the Head of Projects and
Programmes, Asset Management & Regeneration and authorise them
to enter into all other agreements required to deliver this
project.