Bishopgate Street East – Advance Highway & Drainage Works

10/05/2022 - Bishopgate Street East – Advance Highway & Drainage Works

The Chief Officer (Highways and Transportation):
a) Gave authority to spend £497k and appoint Colas via the Leeds Minor Works Framework to deliver drainage and kerb realignment highways works on Bishopgate, in advance of the main project works commencing on site in August 2022; and
b) Gave authority to inject £497k the total cost of the above works into the capital programme. All costs are being funded by WYCA’s TCF programme subject to completion of a variation to the existing Funding Agreement between WYCA and LCC and approval is sought to vary the agreement to this effect.