The Director of Children’s and Families
agreed to:
- Approve the design and cost report
for the scheme at Low Road Primary School, the total cost being
£1.56m (including £96.8k transferred from the PMP
programme) with the appropriate details of the programme, design
and cost as set out in this report; and
- Approve the award of the works to
the Internal Service Provider (ISP), Leeds Building Services, for
the total sum of £978,584 in line with CPR 3.1.5
- Note that no temporary accommodation
is required to accommodate the increase in pupils from September
2017.
- Note that the Chief Officer,
Projects, Programmes & Procurement Unit (PPPU) is responsible
for scheme delivery which is scheduled for completion by 31
December 2017.