The Head of Learning Systems agreed to:
1. Sanction the requirement to enter into an ‘Early
Works’ agreement with the LLEP for ICL to deliver
‘package one’ of the ‘Early Works’
programme necessary to meet the critical path programme for
expansion of Moor Allerton Hall Primary School. This will take the
form of an ‘Early Works’ agreement between the
authority and Leeds D&B One Ltd for the sum of
£127,687.46.
2. Approve the expenditure of £127,687.46 from capital scheme
number 32737/MAL/000 for the completion of ‘package
one’ of the ‘Early Works’ programme at Moor
Allerton Hall Primary School.
3. Note that this constitutes the first of two separate
‘Early Works’ packages required at Moor Allerton Hall
Primary School prior to entering into formal contract in February
2019. Package one, detailed within this report, includes for site
preparation activities and enabling works only.
4. Note the programme dates identified in section 4.0 of this
report, in relation to the implementation of this decision,
represents the critical path for project success and must be
adhered to where possible.
5. Note that the officer responsible for implementation is the Head
of Projects and Programmes, Asset Management &
Regeneration.