The Chief Officer (Highways & Transportation):
i) noted the contents of this report;
ii) noted the highway works as outlined in Section 3 and indicated on Drawing Number 299743-LCC-HWT-PH3-DR-CH-MI_01_ shown as Appendix 1 of this report;
iii) gave authority to complete the detailed design, and implement Phases 3 and 4 works as set out in Section 3 using Highway Maintenance Seacroft Depot as Contractor; and
iv) gave authority to incur expenditure of £900,000 works costs and £100,000 staff fees to be funded from LCC Capital borrowing resources. Phase 3 to be constructed between April 2019 to March 2020, and Phase 4 to be constructed between April 2020 to March 2021.