Details of officer decisions relating to planning applications.
Decision Maker: Director of Resources
Decision published: 15/10/2021
Effective from:
Decision:
To use the ESPO framework contract to select a
provider for leasing ULEV (Ultra Low Emission Vehicles) cars to LCC
staff
Wards affected: (All Wards);
Lead officer: Alex Watson
Decision Maker: Director of Adults and Health
Decision published: 14/10/2021
Effective from:
Decision:
The Director of Adults and Health approved the request in line with
CPR 3.1.6 for authority to procure a counselling and therapy
service for women in Leeds, subject to Schedule 7, Paragraph 27 of
the Equality Act 2010.
The Director of Adults and Health approved the award of a contract
for five years with the option to extend for up to a further five
years to the successful provider(s) following the procurement
exercise, at a maximum cost of £1,290,060 for this period
(£129,060 per annum).
This significant operation decision is an addendum to the original
key decision taken in July 2021 and is to clarify that the request
for authority to procure a service for women only is subject to
Schedule 7, Paragraph 27 of the Equality Act 2010.
A brief statement of the reasons for the decision -
A request for authority to procure a counselling and therapy
service for women is being put forward in this report. The Council
already commissions this provision, and has done since 1983. In
recent years, the existing provider WCTS has been commissioned to
deliver the service via a number of short term interim contracts. A
delegated decision was taken in 2019 to test the market in order to
ensure the Council is achieving value for money. The commencement
of the MSE was delayed due to the Covid-19 pandemic, but was
eventually undertaken in early 2021. Five MSE responses were
received which indicates that there is a potential market locally
for this type of provision. PACS colleagues have therefore advised
that a full market test through open procurement is now
required.
A request to procure a women only service is being put forward
subject to Schedule 7, Paragraph 27 of the Equality Act 2010 as a
proportionate means of achieving a legitimate aim (as detailed
below):
27 Single-sex services
(1) A person does not contravene section 29, so far as relating to
sex discrimination, by providing a service only to persons of one
sex if—
(a) any of the conditions in sub-paragraphs (2) to (7) is
satisfied, and
(b) the limited provision is a proportionate means of achieving a
legitimate aim.
(3) The condition is that—(b) the service would be
insufficiently effective were it only to be provided jointly.
(5) The condition is that the service is provided at a place which
is, or is part of—(b) another establishment for persons
requiring special care, supervision or attention.
(6) The condition is that—(a) the service is provided for, or
is likely to be used by, two or more persons at the same time, and
(b) the circumstances are such that a person of one sex might
reasonably object to the of a person of the opposite sex.
Wards affected: (All Wards);
Lead officer: Eleanor Hastwell
Decision Maker: Director of City Development
Decision published: 13/10/2021
Effective from:
Decision:
The Chief Officer Operations and Active Leeds
approved:
a) Moving to 50 weeks a year of swimming lessons for children and
adult
programmes.
b) Increasing the monthly cost of swimming lesson by direct debit,
removing the need for a Leeds card and providing for the inclusion
of public/family swimming in the swimming lesson direct debit
membership
c) Changing the age of free swimming from under 5 to under 3 years
old for anyone not on the existing swimming lesson
programme.
Wards affected: (All Wards);
Lead officer: Steven Baker
Decision Maker: Director of City Development
Decision published: 13/10/2021
Effective from:
Decision:
The Chief Officer Operations and Active Leeds
has given authority to inject and spend £149,917.20 in
2021/22 supported from prudential borrowing at a cost of £24k
per annum over 7 years on gym equipment for Pudsey Leisure
Centre.
Wards affected: Pudsey;
Lead officer: Catherine Fenton
Decision Maker: Director of Communities, Housing & Environment
Decision published: 13/10/2021
Effective from:
Decision:
The Director of Communities, Housing and
Environment approved use of Ministry of Housing Communities and
Local Government’s (MHCLG) Rough Sleeping Initiative grant of
£212,250, to Barca-Leeds to employ four Navigators, a trainee
Navigator and a Team Leader. Responsibility for implementation of
this decision is the Integrated Commissioning Team, Adults and
Health.
Wards affected: (All Wards);
Lead officer: Susan Skinner
Decision Maker: Director of Communities, Housing & Environment
Decision published: 13/10/2021
Effective from:
Decision:
The Chief Officer, Parks and Countryside
agreed with the proposed changes to seasonal bedding displays and
city centre floral decorations in response to climate change
issues.
Wards affected: (All Wards);
Lead officer: Michael Kinnaird
Decision Maker: Director of Resources
Decision published: 13/10/2021
Effective from:
Decision:
The Chief Officer, Financial Services approved
the sub-delegation scheme set out at Appendix 1.
Wards affected: (All Wards);
Lead officer: Lindsay Dewar
Decision Maker: Director of City Development
Decision published: 12/10/2021
Effective from:
Decision:
Director of City Development has approved
terms for the acquisition of property at Kingsdale Court,
Leeds.
Director of Housing Communities & Environment has approved
expenditure for the acquisition from the Housing Revenue Account
and that the property be added to the Council’s social
housing stock.
Wards affected: Killingbeck and Seacroft;
Lead officer: James Kilroy
Decision Maker: Director of City Development
Decision published: 12/10/2021
Effective from:
Decision:
The Chief Officer (Highways &
Transportation) approved the recommendation to extend funding for
Operation SPARC using an additional £67,000 of funding. This
funding is expected to cover the cost of deployments until summer
2022.
b) Operation SPARC will be implemented by West Yorkshire Police,
with support from and monitoring by Leeds City Council’s
Influencing Travel Behaviour team.
Wards affected: (All Wards);
Lead officer: Lynsey McGarvey
To use Above Threshold Open tendering process as the procurement route to appoint contractors across 9 lots. The contract commencement will be approximately March 2022 for a duration of 4 years with an option to extend for a further 4 x 12 months.
Decision Maker: Director of Resources
Decision published: 12/10/2021
Effective from: 28/10/2021
Decision:
In accordance with the Council’s Contract Procedure Rules 3.1.7, the Director of Resources approved the use of Above Threshold Open tendering process as the procurement route to appoint contractors across 9 lots. The contract commencement will be approximately March 2022 for a duration of 4 years with an option to extend for a further 4 x 12 months.
Lead officer: Craig Simpson
Decision Maker: Director of Communities, Housing & Environment
Decision published: 11/10/2021
Effective from:
Decision:
To cancel annual bonfire and firework displays
at Bramley Park, East End Park, Middleton Park, Roundhay Park,
Springhead Park and Woodhouse Moor due to be held in November
2021.
Wards affected: Various;
Lead officer: Michael Kinnaird
Decision Maker: Director of City Development
Decision published: 11/10/2021
Effective from:
Decision:
The Chief Officer for Culture and Economy has
:
a) approved Leeds City Council’s match funding contribution
of
£62,704 per annum (based on 2021/22 figures) for delivery of
the
Leeds component of LEP Growth Service to March 2023. A total
of £125,408 over the period 2021-23. The Council’s
match funding
contribution is in kind and comes from its contribution to
existing
staff salaries and associated overheads.
b) authorised the signing of a Deed of Variation to the
original
funding agreement between WYCA and LCC.
Wards affected: (All Wards);
Lead officer: David Baggaley
Approval of the acquisition of mines & minerals interests from a third party in east Leeds. The total expenditure will be more than £500,000.
Decision Maker: Director of City Development
Decision published: 11/10/2021
Effective from: 27/10/2021
Decision:
The Director of City Development has given approval to acquire mines and minerals interests under Council owned land in East Leeds as set out in this report.
The Director of City Development has also given approval to the payment for the compulsory acquisition of land and property interests in relation to East Leeds Orbital Route as set out in this report.
Wards affected: Cross Gates and Whinmoor; Harewood;
Lead officer: Mary Stockton
Decisions include approval to receive traded income and reimburse schools and academies for time and expertise associated with providing school to school support through the Leading Learning Partnership (LLP).
Other decisions, which are not Key but will be included in the same decision report are approval to invoke Contract Procedure Rule 7.2 to procure services from Huntington Research School without competition; and approval to hire venues by way of Contract Procedure rule 7.2.
Decision Maker: Director of Children and Families
Decision published: 07/10/2021
Effective from: 23/10/2021
Decision:
The Director of Children and Families approved the following decisions associated with providing school to school support through the LLP for the period 01/04/2021 to 31/03/2026:
• receive traded income of £118,785 per annum for the 11-19 Learning Improvement Team to facilitate the network and reimburse schools and academies to the value of £42,050 per annum for the time and expertise of Learning and Teaching Specialists (LTSs) and one CEIAG lead professional.
• invoke Contract Procedure Rule 7.2 to procure services from Huntington Research School without competition up to the value of £1,500 per annum.
• procure venues, usually school conference facilities, at an estimated cost of £2,000 per annum invoking Contract Procedure Rule 7.2
Wards affected: (All Wards);
Lead officer: Tracey Thomas-Marshall
Decision Maker: Director of Communities, Housing & Environment
Decision published: 06/10/2021
Effective from:
Decision:
To renew membership for 2021/22 to the Housing
Ombudsman Scheme, as the sole provider of this service, at a value
of £123,717.16 in accordance with the council’s
contract procedure rules 9.5 relating to high value
procurements.
Wards affected: (All Wards);
Lead officer: Ian Montgomery
Decision Maker: Director of Communities, Housing & Environment
Decision published: 06/10/2021
Effective from:
Decision:
The Acting Chief Officer has approved -
To to note the content of this report and is requested to approve
the authority to spend against a new replacement litter bin
programme and programme and recycling on the go replacement bin
programme for the next 10 years.
The Chief Officer financial services is recommended to approve the
injection of £450k the capital program funded by prudential
borrowing to give an overall programme of £450k across the 10
year period 2021/22 to 2031/32. Repayments to be met by the Cleaner
Neighbourhoods Team revenue budget.
That Director of Communities and Environment is requested to
:-
• Authorise spend of £400k over the next 10 years for
the provision of replacement litter bins.
• Authorise spend of £50k for the provision of
replacement recycling on the go bins.
Wards affected: (All Wards);
Lead officer: Mark Dolman
Decision Maker: Director of City Development
Decision published: 05/10/2021
Effective from: 05/10/2021
Decision:
The Director of City Development:
1. Grant Approval to Purchase the properties detailed in the
confidential Appendix A at market value as determined by Land &
Property to be returned to Council housing stock.
2. Authorise the required expenditure to enable the programme to
progress the property acquisition(s) detailed in Confidential
Appendix A, giving special consideration to proposed acquisitions
with a net cost greater than the defined purchase budget. These
acquisitions will be funded from the Council Housing Growth
Programme budget, via a combination of Housing Revenue Account
(HRA) borrowing and Right to Buy receipts.
3. Note that Executive Board granted Authority to Spend for the
programme on 24th July 2019.
4. Note that the Chief Officer Housing has approved these
acquisitions, confirming they are suitable to be added back into
council housing stock.
Wards affected: Farnley and Wortley;
Lead officer: Rebecca Storey
Expansion of ‘West Oaks SEN Specialist School and College’ from 350 pupils to 500 pupil with effect from September 2021. The capital project required to achieve this will utilise the former Rose Court facility and, following refurbishment and conversion of the Grade II listed building, form a new SEN school. This will be known as Headingley Learning and will be West Oaks third campus for the wider school.
Decision Maker: Director of Children and Families
Decision published: 05/10/2021
Effective from: 21/10/2021
Decision:
The Director of Children & Families agreed to:
a) Approve the expenditure of £9,767,967 from capital scheme number 33177/RCT/000 for the sufficiency works at West Oaks School to create the ‘Headingley Learning’ Campus. Noting that this figure includes the tender sum in addition to all ancillary costs, for example, consultancy fees, surveys, furniture & equipment, ICT provision, client held contingency etc. It does not include any costs associated with purchase of the site.
b) Authorise acceptance of the tender submitted by the Leeds Local Education Partnership, via Henry Boot Construction Ltd, in the sum of £7,324,441. Noting that this is inclusive of all contract side design and development fees, including the previously approved sum of £1,360,365 necessary to undertake the ‘Early Works’ programme (DDN D54051, D54409 and D54531).
c) Sanction the requirement to enter into a contractual agreement with D&B One Co. to deliver the West Oaks School ‘Headingley Learning’ sufficiency works. This will take the form of a JCT contract between the Authority and Leeds D&B One Ltd. for the sum of £7,324,441.
d) Note that the programme dates identified in section 51 of this report, in relation to the implementation of this decision, represents the critical path for delivery of the project.
Wards affected: Headingley and Hyde Park; Little London and Woodhouse; Wetherby;
Lead officer: Christopher Gosling
Decision Maker: Director of Adults and Health
Decision published: 04/10/2021
Effective from:
Decision:
The Deputy Director, Access & Care
Delivery approved the contents of a report regarding a care plan in
respect of a person with complex care needs, the individual cost of
which is £105,150.96 per annum.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable citizen of the City and the actions being taken to
enable that person to live independently in a safe
environment.
Wards affected: (All Wards);
Lead officer: Shona McFarlane
Decision Maker: Director of Adults and Health
Decision published: 04/10/2021
Effective from:
Decision:
The Deputy Director, Access & Care
Delivery approved the contents of a report regarding a care plan in
respect of a person with complex care needs, the individual cost of
which is £139,199.13 per annum.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable citizen of the City and the actions being taken to
enable that person to live independently in a safe
environment.
Wards affected: (All Wards);
Lead officer: Shona McFarlane
Decision Maker: Director of Adults and Health
Decision published: 04/10/2021
Effective from:
Decision:
The Deputy Director, Access & Care
Delivery approved the contents of a report regarding a care plan in
respect of a person with complex care needs, the individual cost of
which is £102,588.72 per annum.
It is considered in the public interest that information contained
in the report is exempt from publication as it relates to a
vulnerable citizen of the City and the actions being taken to
enable that person to live independently in a safe
environment.
Wards affected: (All Wards);
Lead officer: Shona McFarlane
Decision Maker: Director of City Development
Decision published: 04/10/2021
Effective from:
Decision:
The Chief Officer Asset Management and
Regeneration:
a) Approves entering into an Agreement for Lease as detailed in the
report between LCC and CX (Leeds) Limited (part of Rushbond PLC)
for the construction of a pavilion building.
b) Approves granting a Ground Lease ending on 27 November 2267
(coterminous with the Corn Exchange lease) between LCC and CX
(Leeds) Limited (part of Rushbond PLC) upon satisfactory completion
of the pavilion building within the public space.
c) Approves entering into a user agreement as detailed in the
report between LCC and CX (Leeds) Limited to facilitate use of the
public space by CX (Leeds) Limited for an approved programme of
trading and events.
d) Notes that an overview of the terms of the agreements is
provided at confidential appendix C.
Wards affected: Hunslet and Riverside; Little London and Woodhouse;
Lead officer: Annabel Phipps
Decision Maker: Director of City Development
Decision published: 04/10/2021
Effective from:
Decision:
The Chief Officer Asset Management and
Regeneration has given approval to the marketing of 16 – 22
Burley Street on the open market by way of inviting offers. A
further approval will be sought to any provisionally agreed
transaction.
Wards affected: Little London and Woodhouse;
Lead officer: Kelly Bligh
Decision Maker: Director of Children and Families
Decision published: 04/10/2021
Effective from:
Decision:
Approve the injection of £123,429 of
s106 contribution into the capital programme
Approve authority to spend and incur expenditure of £123,429
from capital scheme number 33177/BGE/GAR to deliver the works
required to allow Garforth Academy to take an additional 25 places
in Year 7 from September 2021.
Note that Children’s & Families Good Learning Places
Board approved the use of s106 reference 11/02814 to fund the cost
of capital works at Garforth Academy
Note that the officer responsible for implementation is the Head of
Service Learning Systems in Children’s and Families
Directorate.
Wards affected: Garforth and Swillington;
Lead officer: Adele Robinson
Decision Maker: Director of City Development
Decision published: 04/10/2021
Effective from: 04/10/2021
Decision:
The Director of City Development:
1. Authorised the required expenditure to enable the programme to
progress the property acquisition(s) detailed in Confidential
Appendix A. These acquisitions will be funded from the Council
Housing Growth Programme budget, via a combination of Housing
Revenue Account (HRA) borrowing and Right to Buy receipts.
2. Note that Executive Board granted Authority to Spend for the
programme on 24th July 2019.
3. Note that the Chief Officer Housing has approved these
acquisitions, confirming they are suitable to be added back into
council housing stock.
Wards affected: Armley; Killingbeck and Seacroft; Kirkstall; Morley North; Morley South;
Lead officer: Rebecca Storey
Brief Description |
Authority to award contracts for the 3rd year allocation from Household Waste Site Recycling Framework (DN 370317) |
Impact On Wards |
All |
Financial and procurement implications |
Approximately £2.6m per year |
Partnership working |
None |
Decision Maker: Director of Communities, Housing & Environment
Decision published: 04/10/2021
Effective from: 20/10/2021
Decision:
The Chief Officer for Environmental Services approves the appointment of the following tenderers as suppliers under Year 3 (1st October 2021 to 30th September 2022) of the Household Waste Site Recycling Framework. Estimated value of the Call Off is £2.8m
Lot Description |
Contractors Appointed |
Sites Proposed |
|
1 |
Residual Waste |
Associated Waste Management Ltd |
Gelderd Road, Gildersome |
Valley Farm Road, Stourton |
|||
2 |
Timber |
Timberpak Ltd. |
Cross Green, Leeds |
3 |
Inert Waste |
Associated Waste Management Ltd |
LSS, Cross Green |
4 |
Plasterboard |
Associated Waste Management Ltd |
LSS, Cross Green |
Valley Farm Road, Stourton |
Wards affected: (All Wards);
Lead officer: Rosie Harvey
Decision Maker: Director of Children and Families
Decision published: 01/10/2021
Effective from:
Decision:
a) Sanction the requirement to enter into an
‘Early works’ agreement with the LLEP for Henry Boot
Construction Ltd to deliver the third package of the ‘Early
Works’ programme necessary to meet the critical path
programme for renovation and refurbishment of the Buckingham Road
Site to create West Oaks School ‘Headingly Learning’.
This will take the form of an ‘Early Works’ agreement
between the Authority and Leeds D&B One Ltd for the sum of
£495,644.53.
b) Approve the expenditure of £495,644.53 from capital scheme
number 33177/RCT/000 for the completion of the ‘Early
works’ programme at West Oaks ‘Headingley
Learning’.
c) Note the programme dates identified in section 39 of this
report, in relation to the implementation of this decision,
represents the critical for project success and must be adhered to
where possible.
d) Note that the officer responsible for implementation is the Head
of Service Learning Systems.
Wards affected: Headingley and Hyde Park;
Lead officer: Adele Berry
Decision Maker: Director of Children and Families
Decision published: 01/10/2021
Effective from:
Decision:
The Built Environment Lead Officer accepted
the tender supplied by
Leeds Building Services in the sum of £168,695.92 to
carry out Mechanical Works at Quarry Mount Primary School.
Wards affected: Headingley and Hyde Park; Little London and Woodhouse;
Lead officer: Adele Berry
Decision Maker: Director of City Development
Decision published: 01/10/2021
Effective from:
Decision:
The Director of City Development has approved
the following in relation to the Covid-19 Additional Restrictions
Grant (ARG) Allocation:
• To reopen the Council’s Covid-19 Discretionary Grant
Fund to new
applications against the grant criteria set out in appendix 1 of
the attached
Decision Report.
• To aim to have the Grant Fund open for a period of up to
four weeks in
October 2021 to enable grant applicants to apply through an
online
application form accessible through the Council’s
website.
• To report progress on a regular basis including the number
of grant
applications received, those approved and paid to ensure that the
Council
maximises the Additional Restrictions Grant allocation from which
grants
are made.
• To ensure that where possible (and subject to the level of
demand) grant applications are appraised and paid within twelve
weeks of receiving all the information required to assess an
application.
Wards affected: (All Wards);
Lead officer: Phil Cole
Decision Maker: Director of Resources
Decision published: 01/10/2021
Effective from:
Decision:
The Chief Officer Financial Services has
approved the request from Labcorp Drug Development for business
rates relief at £335,000 over a three year period from
FY21/22 and the rates relief be released incrementally over 3 years
as follows: 40% in FY 2021/22 (£134,000), 40% in 2022/23
(£134,000) and 20% in 2023/24 (£67,000).
Wards affected: Beeston and Holbeck;
Lead officer: Tariq Sadiq
The Director of Communities, Housing and Environment has –
Approved authority to proceed with a competitive procurement process, as outlined in this report and in line with Contract Procedure Rules (CPRs) 3.1.7, to procure a suitable provider/consortium to deliver a new street outreach service.
Approved a contract period of five years commencing 1st April 2022 (with an option to extend for a period of up to 36 months in any combination), with a maximum budget of £215,000 per annum (£1,720,000 for the overall contract period should the full extension period be taken up).
Decision Maker: Director of Communities, Housing & Environment
Decision published: 29/09/2021
Effective from: 15/10/2021
Decision:
The Director of Communities, Housing and Environment has –
Approved authority to proceed with a competitive procurement process, as outlined in this report and in line with Contract Procedure Rules (CPRs) 3.1.7, to procure a suitable provider/consortium to deliver a new street outreach service.
Approved a contract period of 5 years commencing 1st April 2022 (with an option to extend for a period of up to 36 months in any combination), with a maximum budget of £215,000 per annum (£1,720,000 for the overall contract period should the full extension period be taken up).
Wards affected: (All Wards);
Lead officer: Eleanor Clark
Decision Maker: Director of Communities, Housing & Environment
Decision published: 12/08/2021
Effective from: 11/10/2021
Decision:
The Director of Communities, Housing and
Environment approved the allocation of £220,000 as a grant
(payable in instalments) to CGL to employ six Assertive Street
Outreach Workers (four already in post and two to be recruited);
and a further £4,095 to CGL to provide needs led additional
weekend outreach support work for a 9 month period. Responsibility
for implementation of this decision is the Integrated Commissioning
Team, Adults and Health.
Wards affected: (All Wards);
Lead officer: Susan Skinner