Decisions

Details of officer decisions relating to planning applications.

Decisions published

05/05/2021 - Section 116 Highways Act 1980 – Stopping Up Order Craven Road West Oaks School, Leeds LS6 ref: 54053    Recommendations Approved

Decision Maker: Director of City Development

Decision published: 05/05/2021

Effective from:

Decision:

The Chief Officer, Highways and Transportation;

Instructed the City Solicitor to apply to the magistrates’ court for a stopping up order under Section 116 of the Highways Act 1980 for the area of adopted footway as shown in red on drawing SD/217960/Z239/01.

Wards affected: Little London and Woodhouse;

Lead officer: Michael De-Lucchi


05/05/2021 - Design Cost Report for the ‘Early Works’ package for the expansion of West Oaks School at the former Rose Court building ref: 54051    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 05/05/2021

Effective from:

Decision:

The Head of Service Learning Systems agreed to:
a) Sanction the requirement to enter into an ‘Early Works’ agreement with the LLEP for Henry Boot Construction Ltd. to deliver the ‘Early Works’ programme necessary to meet the critical path programme for renovation and refurbishment of the Buckingham Road site to create West Oaks School ‘Headingley Learning’. This will take the form of an ‘Early Works’ agreement between the Authority and Leeds D&B One Ltd for the sum of £368,936.97.

b) Approve the expenditure of £368,936.97 from capital scheme number 33177 / RCT / 000 for the completion of the ‘Early Works’ programme at West Oaks School ‘Headingley Learning’.

c) Note the programme dates identified in section 3.2 of this report, in relation to the implementation of this decision, represents the critical path for project success and must be adhered to where possible.

d) Note that the officer responsible for implementation is the Head of Service Learning Systems.

Wards affected: Headingley and Hyde Park;

Lead officer: Christopher Gosling


13/05/2021 - St George House - declaring surplus to operational requirements, adding to the Council's Investment Portfolio and approval of lease terms ref: 54054    

Approval to declare St George House surplus to operational requirements, add the asset to the Council’s Investment Portfolio and grant a lease to a new tenant.

Decision Maker: Director of City Development

Decision published: 05/05/2021

Effective from: 21/05/2021

Decision:

The Chief Officer Asset Management and Regeneration has

i) Declared St George House surplus to operational requirements;

ii) Approved the realignment of St George House to the Council Investment Property Portfolio; and

iii) Approved the Heads of Terms as identified in the exempt appendix to enable a lease to be put into effect between the Council and the named tenant.

Wards affected: Little London and Woodhouse;

Lead officer: Paul Fleming


30/04/2021 - Leeds City Centre West Spatial Analysis ref: 54050    Recommendations Approved

Decision Maker: Director of City Development

Decision published: 30/04/2021

Effective from:

Decision:

The Chief Officer for Asset Management and Regeneration
i. Agreed to the scope and programme of the spatial analysis and approved the method of procurement as summarised below;
ii. Approved the proposed evaluation and scoring method;
iii. Approved the waiver of Contracts Procedure Rule 15.2 – Tender evaluation, in order to set the evaluation criteria split as 30% for price and 70% for quality.

Wards affected: Hunslet and Riverside; Little London and Woodhouse;

Lead officer: Sarah Parry


30/04/2021 - Approval of a care plan to the value between £100,000 and £500,000 per annum. ref: 54049    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 30/04/2021

Effective from:

Decision:

The Director, Children & Families agreed the recommendation of a report relating to the placement of a child/young person. The individual costs of the place are £317,252.00.

It is considered in the public interest that information contained in the report is exempt from publication as it relates to a vulnerable child or young person of the City and the actions being taken to enable that person to live in a safe environment.

Wards affected: Various;

Lead officer: Ruth Terry


30/04/2021 - Approval of a care plan to the value between £100,000 and £500,000 per annum ref: 54048    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 30/04/2021

Effective from:

Decision:

The Director, Children & Families agreed the recommendation of a report relating to the placement of a child/young person. The individual costs of the place are £547,500.00.

It is considered in the public interest that information contained in the report is exempt from publication as it relates to a vulnerable child or young person of the City and the actions being taken to enable that person to live in a safe environment

Wards affected: Various;

Lead officer: Ruth Terry


30/04/2021 - COVID Local Support Grant ref: 54047    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 30/04/2021

Effective from:

Decision:

The Director of Children and Families agreed to;
a) Accept the £667,660 COVID Local Support Grant funding from the Department for Work and Pensions.
b) Agree for the COVID Local Support Grant funding to be principally used to provide meals for children eligible for free school meals and children living in low income households over May 2021 half term. For the remaining funding to be used to support vulnerable families and individuals with the costs of food, fuel and essential items.

Wards affected: (All Wards);

Lead officer: Joanna Rowlands


30/04/2021 - Appointment of providers to the White Rose Special Educational Needs and Disabilities Electronic Marketplace agreement DN510309 as a result of the competitive exercise. ref: 54045    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 30/04/2021

Effective from:

Decision:

The Director of Children and Families approved decision reference D52545 to undertake a competitive procurement exercise to establish the regional White Rose special education needs and disabilities (SEND) Electronic Market Place and to appoint providers onto the agreement commencing on 1st July 2021 and expiring on 30th June 2025 with the option to extend for up to 24 months. As a consequence of this decision, a full procurement exercise was undertaken and a number of providers have been approved for appointment to the SEND EMP from which they can bid for placements advertised by local authorities who are members of the White Rose Partnership. Providers approved for immediate appointment are listed at Appendix 1.
Due to the Covid 19 pandemic, Ofsted were unable to carry out a first inspection of some new settings. A route to access this agreement for yet to be rated providers and/or settings was described within the specification along with the process for additional quality assurance work. The providers falling into this category are identified in Appendix 2. This process is yet to be completed and will result in further appointments to the SEND EMP when a satisfactory quality check is complete.

Wards affected: (All Wards);

Lead officer: Kate Sibson


11/05/2021 - Approval to procure a contractor to undertake repair and improvement works to the Marlborough Towers high rise block ref: 54023    Recommendations Approved

Concrete Repairs and Improvement works to Marlborough Towers and the  surrounding estate.

Decision Maker: Director of Communities, Housing & Environment

Decision published: 30/04/2021

Effective from: 19/05/2021

Decision:

The Director of Communities, Housing and Environment: 

a)  Approved this scheme of repair and improvement works to Marlborough Towers high rise block.

b)  Approved the competitive procurement of an external contractor, which is planned through the Efficiency North Framework, and;

c)  Authorised spend of £2.5m from the Housing capital programme over the financial years of 2021/22 to 2022/23 for the Marlborough’s Improvement Scheme phase 1 works to Marlborough Towers.

Wards affected: Little London and Woodhouse;

Lead officer: Paul Rounding


30/04/2021 - Approval of a care plan to the value between £100,000 and £500,000 per annum ref: 54046    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 30/04/2021

Effective from: 30/04/2021

Decision:

The Deputy Director, Children & Families agreed the recommendation of a report relating to the placement of a child/young person.  The individual costs of the place are £184,061.68.

It is considered in the public interest that information contained in the report is exempt from publication as it relates to a vulnerable child or young person of the City and the actions being taken to enable that person to live in a safe environment.

 

Wards affected: Various;

Lead officer: Ruth Terry


29/04/2021 - City Centre Vehicle Access Management System (CCVAMS) Maintenance Contract – Approval for Tender ref: 54044    Recommendations Approved

Decision Maker: Director of City Development

Decision published: 29/04/2021

Effective from:

Decision:

The Chief Officer (Highways & Transportation) approved the recommendation to tender the City Centre Vehicle Access Management System (CCVAMS) Maintenance Contract using the evaluation criteria and specification within the contract documents to assess submitted tenders.

Wards affected: (All Wards);

Lead officer: James Hirst


28/04/2021 - Authority to extend contract number DN380443 Postgraduate SENCO training. ref: 54042    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 28/04/2021

Effective from:

Decision:

The Director of Children and Families approved the three year extension provision on contract DN380443 with Leeds Trinity University to run a postgraduate qualification for school based special educational needs co-ordinators (SENCOs) from 1st June 2021 to 31st May 2024. The value of the contract is estimated at £300,000 however places on the course are fully funded by the schools with no cost to the Local Authority.

Wards affected: Various;

Lead officer: Kate Sibson


28/04/2021 - Design & Cost Report for additional works associated with the Learning Places expansion of Carr Manor Community School (Primary Phase) ref: 54041    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 28/04/2021

Effective from:

Decision:

The Head of Service, Learning Systems agreed to:
1. Approve the expenditure of £264,245.96 from capital scheme number 32655/CAR/000 for the remaining works necessary to complete the Learning Places Expansion of Carr Manor Community School.

2. Note that the original ‘approval to spend’ figure for the Carr Manor Community School project was £5m, of which £4,674,243.89 has been drawn down previously.

3. Note that the officer responsible for implementation is the Head of Service Learning Systems and the Head of Projects and Programmes, Asset Management & Regeneration and authorise them to enter into all other agreements required to deliver this project.

Wards affected: Moortown;

Lead officer: Christopher Gosling


28/04/2021 - Extension of the Discharge to Assess Frameworks (DN501376 & DN511940) ref: 54040    Recommendations Approved

Decision Maker: Director of Adults and Health

Decision published: 28/04/2021

Effective from:

Decision:

The Director of Adults and Health:-

a) Extended both framework contracts (DN501376 & DN511940) for a further period of 2 months from the 1st May 2021 to the 30th June 2021 as permitted under the framework terms to the list of providers in Appendix 1.

b) Noted the Commissioning Manager for Older People’s Services will issue the framework extension letters once the decision has been approved.

Wards affected: (All Wards);

Lead officer: Mark Phillott


07/05/2021 - Authority to procure contractors to undertake Damp Proofing Prevention Works Including Timber Treatment ref: 54043    For Determination

Approval needed to undertake procurement of up to 2 specialist contractors to support LBS with damp proofing prevention works including, timber treatment to Leeds City Council Leeds City Council domestic occupied and unoccupied (voids) properties.

Currently, there is no contract in place for Damp Proofing Services and this requirement is being carried out by multi trade contractors under an interim arrangement. This new contract will cover the East, and South of the City with an expected start date in July 2021 for the duration of 2years plus 2 x 12 months possible extension.

Decision Maker: Director of Resources

Decision published: 28/04/2021

Effective from: 15/05/2021

Decision:

The Director of Resources approved the use of a restricted constructionline tendering process as the procurement route to establish a framework of 2 contractors. This framework will start 1st July 2021 for a duration of 2 years with an option to extend for a further 2 x 12 months. The value is estimated at £244,000 per annum and a potential total framework value of £976,000.

Wards affected: (All Wards);

Lead officer: Craig Simpson


27/04/2021 - Arena Development Plots, Clay Pit Lane, Leeds ref: 54039    Recommendations Approved

Decision Maker: Director of City Development

Decision published: 27/04/2021

Effective from:

Decision:

Approval has been given to the final terms, as outlined in the confidential appendix, for a land exchange to to facilitate the creation of a single larger development plot, which can be brought forward for a potential future complementary use to the Arena.

Wards affected: Little London and Woodhouse;

Lead officer: James Child


27/04/2021 - Ex-council properties to be acquired by the Council and returned to council housing stock. Capital Scheme number 33103 ref: 54038    Recommendations Approved

Decision Maker: Director of City Development

Decision published: 27/04/2021

Effective from:

Decision:

The Chief Officer Asset Management and Regeneration has approved the purchase of a property on the terms detailed in the confidential appendix for Resources and Housing to return to Council stock.

Wards affected: Various;

Lead officer: Diane McPhee, Rebecca Storey


27/04/2021 - Creation of a new temporary Commissioning Programme Leader post to lead a redesign team for the home care service in the city ref: 54037    Recommendations Approved

Decision Maker: Director of Adults and Health

Decision published: 27/04/2021

Effective from:

Decision:

The Director of Adults and Health has -

a) Approved the establishment of a temporary Commissioning Programme Leader post within the commissioning structure at the grade of PO6 for a period of 2 years to work on the redesign of home care project.

b) Noted that the Head of Commissioning will seek to establish the post through the HR process, immediately following the decision being made.


Wards affected: (All Wards);

Lead officer: Mark Phillott


26/04/2021 - Approval of the Director of Children and Families Sub-delegation Scheme ref: 54035    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 26/04/2021

Effective from:

Decision:

The Director of Children & Families approved the sub-delegation scheme set out at Appendix 1.

Wards affected: (All Wards);

Lead officer: Lindsay Dewar


05/05/2021 - Design and Cost Report in respect of the 2021/22 Children and Families Planned Maintenance Programme ref: 54036    Recommendations Approved

Key Delegated Decision to approve expenditure over £500k in respect of the 2021/22 Planned Maintenance Programme.

Decision Maker: Director of Children and Families

Decision published: 26/04/2021

Effective from: 13/05/2021

Decision:

The Director of Children and Families agreed to:

a)  Approve the proposed programme of Planned Maintenance works in maintained and Foundation (Trust) schools to be delivered during 2021/22 and funded from the available Schools Condition Allocation grant provided by the DfE.

b)  Authorise expenditure of £4,500,000 of the available Schools Condition Allocation grant on these essential condition works.

c)  Approve the proposed procurement strategy, using the in-house Procurement Team, and the use of the internal provider for some work areas and the Constructionline framework for the remaining programme.

d)  Noted that £250,000 of previous year’s School Condition Allocation with pre-existing Authority to Spend is still available to be utilised towards the 2020/21 Capital Maintenance Programme, based on current outturn projections for previous year’s maintenance schemes.

 

 

Wards affected: (All Wards);

Lead officer: Sally Lowe


21/04/2021 - Outcome of statutory notice on a proposal to establish Resource Provision at St Margaret's Church of England Primary School from September 2021 ref: 54032    Recommendations Approved

Outcome of statutory notice on a proposal to establish Resource Provision at St Margaret’s Church of England Primary School from September 2021.

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 21/04/2021

Decision:

Further to Minute No. 127, 10th February 2021, the Director of Children and Families submitted a report presenting the outcomes from the statutory notice published under the Education and Inspections Act 2006 and in accordance with the School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2013 regarding a proposal to establish a 12 place Resource Provision for pupils with complex communication difficulties including Autistic Spectrum Condition at St. Margaret’s Church of England Primary School, and which sought a final decision in respect of that proposal.

 

RESOLVED –

(a)  That the proposal to establish a 12 place Resource Provision for pupils with complex communication difficulties including Autistic Spectrum Condition (ASC) at St. Margaret’s Church of England Primary School in Horsforth with effect from September 2021, be approved;

 

(b)  That approval be given to exempt the resolutions arising from the submitted report, as detailed within this minute from the Call In process for the reasons as set out in paragraph 4.5.2 of that report;

 

(c)  That it be noted that the responsible officer for the implementation of such matters is the Head of Learning Systems.

 

(The Council’s Executive and Decision Making Procedure Rules state that a decision may be declared as being exempt from the Call In process by the decision taker if it is considered that the matter is urgent and any delay would seriously prejudice the Council’s, or the public’s interests. In line with this, the resolutions contained within this minute were exempted from the Call In process, as per resolution (b) above, and for the reasons as detailed within section 4.5.2 of the submitted report)

Wards affected: Horsforth;

Lead officer: Vivienne Buckland


21/04/2021 - Youth Work Review and Future Vision ref: 54033    Recommendations Approved

To endorse the vision for youth work in Leeds and approve the proposed new model of youth work delivery.

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 01/05/2021

Decision:

The Director of Children and Families submitted a report that presented the findings from the review which had been undertaken into Youth Work in Leeds, and which outlined the vision for youth work together with the proposals for future delivery.

 

In introducing the report, the Executive Member highlighted the extensive consultation which had been undertaken to inform the proposed model, and it was highlighted that no single Ward would receive any less Council delivered youth work provision than what was currently being received, but that moving forward a greater focus would be placed upon the city’s more deprived communities and neighbourhoods with the greatest need.

 

Members welcomed proposals to establish a more collaborative approach between communities and youth work provision, and in response to a Member’s enquiry, the Board received further detail on the provision that was currently in place and what was proposed as part of the new model to support those pockets of deprivation located in more affluent areas.

 

RESOLVED –

(a)  That the comprehensive consultation and assessment work which has been undertaken to develop the vision for youth work in Leeds, be noted, and that the continuing commitment to youth services as a key strand of work to enable the most vulnerable young people in the city achieve their aspirations and ambitions, be endorsed;

 

(b)  That the proposed new model of youth work delivery, as detailed within the submitted report, be approved, and that support be given to further work being undertaken which will be led by the Youth Offer Lead in order to co-produce the enhanced youth work specification;

 

(c)  That it be noted that the new model of youth work delivery will be fully implemented by April 2022.

 

Lead officer: Vicky Fuggles


21/04/2021 - Responding to the Levelling Up Fund ref: 54027    Recommendations Approved

To agree approach to assessing and prioritising submission of bids to the government’s Levelling Up Fund.

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 01/05/2021

Decision:

The Director of City Development submitted a report which set out proposals for how the Council intended to respond to the Government’s ‘Levelling Up’ Fund, which was released as part of the March 2021 Budget, with it being noted that the related prospectus presented an opportunity to bid for significant capital investment for the delivery of projects from the 2021/22 financial year.

 

As part of the introduction to the report, the Board noted the intention for an additional meeting of the Board to be held prior to the submission of any bid(s) and before the 18th June 2021 Round 1 Levelling Up Fund submission deadline, to consider the proposals.

 

Responding to a Member’s enquiry, in acknowledging the tight timeframe involved, the Board received further detail and assurance that consultation would take place with local MPs in line with the Fund’s requirements. In addition, it was noted that consultation would also take place with local Ward Councillors, initially with those Members affected by the proposals being considered for Round 1 submission, with the same principle for Ward Councillor engagement being used for future rounds when those details were known.

 

In considering the report a Member commented upon the need for all communities in Leeds to have equal opportunity to access this and other funding streams; highlighted the longer term and collaborative approach required to enable districts and communities to maximise the benefit from such funding, and enquired whether this could potentially be an area for future consideration by the Board.

 

In response, Members were provided with further detail regarding average levels of potential funding available per constituency and per Priority 1 Local Authority area, with any funding secured being subject to Leeds’ success in the bidding process. Also, emphasis was placed upon the importance of Leeds, and all communities within it, maximising the benefit from all external funding streams which were being made available, with the potential benefits from a longer term approach towards such matters being acknowledged.

 

RESOLVED –

(a)  That the approach, as detailed within the submitted report, to bringing forward bids to the Levelling Up Fund, be noted and supported, with it being agreed that constituency MP’s within the Leeds Metropolitan District boundary are asked to indicate their priorities for investment, so that these can be taken into consideration by the Council;

 

(b)  That agreement be given for the Director of City Development to undertake an assessment and a prioritisation of projects for the Levelling Up Fund in consultation with relevant Executive Members, as set out in paragraphs 3.4 – 3.11 of the submitted report;

 

(c)  That agreement be given for proposals for Round 1 bids to be considered at an additional meeting of Executive Board to take place prior to the submission of any bid(s) and before the 18th June 2021 Levelling Up Fund submission deadline;

 

(d)  That the intention to bring a further report to Executive Board be noted, which will relate to the submission of bids for future rounds of the Levelling Up Fund and in relation to any changes to the Government prospectus and guidance.

 

Lead officer: Adam Brannen


21/04/2021 - Proposed Grey to Green Projects - Progress Update ref: 54028    Recommendations Approved

Executive Board will be asked to

Note the progress made to date with the development of the Grey to Green programme following the successful bid to the Getting Building Fund and the development of the three projects: Meadow Lane Greenspace; Sovereign Street Bridge and Crown Point Road calming and greening.

 

Approve the design proposals developed for the creation of Meadow Lane Green Space as part of the Council’s ongoing commitment to the development of green infrastructure in the city centre to support the implementation of the Our Spaces Strategy and the South Bank Regeneration Framework Supplementary Planning Document and give approval to the progression of the scheme presented into the next phase of detailed and technical design.

 

Approve the design proposals developed to date for Sovereign Street Bridge and the submission of a planning application for the bridge to enable the continued progression of the scheme.

 

Approve the layout proposals developed to date for the Crown Point Road calming and greening scheme and give approval to the progression of the scheme into the next phase of design.

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 01/05/2021

Decision:

Further to Minute No. 125, 10th February 2021, the Director of City Development submitted a report providing an update on the progress of the ‘Grey to Green’ infrastructure projects following the successful ‘Getting Building Fund’ submission in September 2020 and the subsequent Full Business Case approval at the West Yorkshire Combined Authority Investment Committee in February 2021. The report also sought approval of the designs developed to date for each scheme and their progression into the detailed design and planning submission phase, together with the necessary ‘Authority to Spend’ of the allocated funding identified for each scheme.

 

Responding to a Member’s enquiry, the Board was provided with information on how the principles of the proposed schemes remained appropriate when taking account of the current economic position and the evolving ways of working and living as a result of the pandemic.

 

Members also discussed the decision making processes by which the final business case for the projects had been approved by the Combined Authority and given the advanced stage at which these projects were at, it was felt that any risk of further intervention by the Combined Authority or Mayoral Authority was minimal.   

 

The Board discussed the associated timeframes for this funding process, whilst a Member reiterated his earlier comment about the need for communities outside of the city centre to have an opportunity to access appropriate funding streams moving forward.

 

RESOLVED –

(a)  That the progress which has been made to date regarding the development of the ‘Grey to Green’ programme following the successful bid to the ‘Getting Building Fund’, be noted, with the development of the three projects, namely: Meadow Lane Greenspace; Sovereign Street Bridge and Crown Point Road calming and greening, also being noted;

 

(b)  That the design proposals developed for the creation of Meadow Lane Green Space as part of the Council’s ongoing commitment to the development of green infrastructure in the city centre to support the implementation of the ‘Our Spaces’ Strategy and the South Bank Regeneration Framework Supplementary Planning Document, be approved, and that approval also be given to the progression of the scheme, as presented, into the next phase of detailed and technical design;

 

(c)  That the design proposals developed to date for Sovereign Street Bridge, be approved, and that approval also be given for the submission of a planning application for the bridge, in order to enable the continued progression of the scheme;

 

(d)  That the indicative layout proposals developed to date for the Crown Point Road calming and greening scheme, be approved, and that approval also be given for the progression of the scheme into the next phase of design;

 

(e)  That it be noted that the Director of City Development will be responsible for the implementation of such matters, as detailed within the submitted report, and the resolutions, as above.

 

Wards affected: Hunslet and Riverside;

Lead officer: Jane Cash


21/04/2021 - City Centre Transformation - Enabling Schemes (Highways) ref: 54029    Recommendations Approved

Executive Board will be asked to:

a)  Approve the outline design for the highway proposals for City Square

b)  Approve the preliminary design of Armley Gyratory subject to any changes arising from Planning conditions or the detailed design process;

c)  Note the delivery with a target completion date of December 2022.

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 01/05/2021

Decision:

Further to Minute No. 79, 18th November 2020, the Director of City Development submitted a report which sought approval of the outline highway design concept for the closure of City Square and its subsequent implementation in readiness for the Year of Culture. The report also sought approval of the preliminary design and implementation of Armley Gyratory, subject to any Planning conditions and detailed design changes.

 

Regarding the potential inclusion of water features within the design for the City Square proposals, Members were assured that the images within the submitted report were indicative only and that the related design competition continued. However, should water features be included in the final design it was acknowledged that appropriate due diligence would need to be undertaken and resource allocated to ensure the long term maintenance of them. On this point, the Director of City Development offered to provide relevant Executive Members with further information regarding the specific challenges of maintaining public water features, if required.

 

In relation to the proposals, a Member highlighted the importance of ensuring that they did not deter visitors to the city centre via car or any other means of transport. Also, an enquiry was raised regarding how the proposals would impact upon the flow of traffic in the city centre and how they would affect air quality. In response, it was noted that detailed transport modelling work on issues such as air quality would continue as part of the respective Combined Authority and planning processes. Also, it was highlighted that the proposals would aim to maximise ‘movement capacity’ for all forms of transport, with it being emphasised that the proposals did not aim to stop cars from accessing the city centre.

 

Specifically regarding the proposals for Armley Gyratory, a Member highlighted the issue of users’ safety, with reference being made to those accessing the Gyratory via active travel and also when considering female users’ safety. In response, it was confirmed that such matters were being taken into consideration as part of the design work, with reference being made to landscaping, lighting, connectivity and users’ general visibility when travelling through the Gyratory. In conclusion, it was noted that Executive Members’ suggestions regarding the design proposals would be welcomed.

 

RESOLVED –

(a)  That in the context of previous decisions taken by Executive Board, and as outlined within the submitted report, the outline design for the closure of City Square to through traffic, as per the plan in Appendix 1, including the indicated bus and taxi only restrictions, be approved, with it being noted that at the discretion of the Chief Officer (Highways and Transportation), there may be further adjustments to the design in order to respond to stakeholders’ needs and the proposed public consultation;

 

(b)  That the preliminary design of Armley Gyratory, as shown in Appendix 1 to the submitted report and as presented in the recent engagement, be approved, subject to any changes arising from Planning conditions or the detailed design process;

 

(c)  That it be noted that the City Square closure (highway works) and Armley Gyratory are to be fully funded from the West Yorkshire Plus Transport Fund;

 

(d)  That the importance of the delivery of the Highways England M621 Road Investment Strategy (RIS) scheme (Junctions 1 to 7) for the realisation of the city centre vision, be noted;

 

(e)  That it be noted that the Chief Officer (Highways and Transportation) is responsible for the associated programme delivery, with a target completion date of December 2022.

Wards affected: Armley; Beeston and Holbeck; Hunslet and Riverside; Little London and Woodhouse;

Lead officer: Mark Philpott


21/04/2021 - Update on Coronavirus (COVID19) pandemic – Response and Recovery Plan ref: 54030    Recommendations Approved

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 01/05/2021

Decision:

Further to Minute No. 144, 17th March 2021, the Chief Executive submitted a report which provided an update on the Covid-19 Response and Recovery Plan, as well as the Local Outbreak Management Plan, which in the last month had included: the safe reopening of businesses; continued work and proactive communications with communities and services in line with the national recovery roadmap; the vaccination rollout and the tackling of health  inequalities in this area; outbreak management work, including testing, tracing and support to self-isolate; and further action in the areas of compliance and enforcement.

 

With the agreement of the Chair, the submitted report had been circulated to Board Members as a late item of business prior to the meeting for the reasons as set out in section 11.12 of the submitted report, and as detailed in Minute No. 150.

 

By way of introduction to the report, it was highlighted that 1,608 people had died in the city as a result of Coronavirus to date. On behalf of the Council, the Leader extended his sympathies to the families and loved ones of all those who had lost their lives. 

 

The Leader also noted that over the past week, the infection rate in Leeds had reduced by 32%, which was below the Yorkshire and Humber average.

 

Responding to a Member’s enquiries, the Director of City Development undertook to provide further detail to relevant Executive Members regarding the grant which had been received from Arts Council England’s Cultural Recovery Fund, in terms of what the funding was intended to be used for and on which sites.

 

Also, further detail was provided regarding the ongoing citywide ‘conversation’ on the future use of city and local centres and how they will be used in the longer term as we continue to move through the pandemic, with the Director offering to provide the Member in question with a briefing on this matter, if required.

 

Regarding a Member’s enquiry on the current position relating to the backlogs for treatment in hospital settings, the Director of Public Health undertook to make enquiries on such matters and provide further detail to the Member in question.

 

Also, regarding the provision of grants for businesses which were administered by the Council, responding to an enquiry, the Board received an update on the current position regarding the allocation and distribution of grants, together with details on the actions being taken to deliver such funding as efficiently as possible, and working to the Government’s deadline of end of June 2021, with the Member in question being offered a separate briefing on such matters.

 

RESOLVED –

(a)  That the Response and Recovery Plan, as appended at Annex A to the submitted report, together with the full range of activity taking place to prepare for the safe reopening of services and the economy in the coming months, be noted, with the focus on planning for the year ahead also being noted;

 

(b)  That the current position with regard to the four measures in the Roadmap, be noted, and that the continued need for everyone to play their part while restrictions remain in place, be recognised and emphasised;

 

(c)  That the refreshed Local Outbreak Management Plan, as detailed at Annex C to the submitted report, be agreed, and that the continued proactive approach being taken towards all aspects of the plan, including vaccinations, testing, tracing, support to self-isolate, support to businesses, communications, compliance and enforcement, be noted;

 

(d)  That in respect of the financial implications for the Council arising from the Coronavirus pandemic, the content of the submitted report be used as context when the Board considers the more detailed finance based report as referenced at Minute No. 158;

 

(e)  That in respect of the issue of addressing health inequalities in relation to the uptake of the Covid-19 vaccination across all communities in Leeds, the content of the submitted report be used as context when the Board considers the more detailed report on such matters as referenced at Minute No. 153.


21/04/2021 - Financial Health Monitoring 2020/21 – Provisional Outturn ref: 54031    Recommendations Approved

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 01/05/2021

Decision:

The Chief Officer (Financial Services) submitted a report which set out the Council’s projected provisional financial outturn position for 2020/21 in respect of both the General Fund revenue budget and also the Housing Revenue Account.

 

In considering the submitted report, Members welcomed the provisional balanced budget position for 2020/21 which was presented, and extended their thanks to all those who had helped achieve this position, given the significant challenges which had been faced throughout the year.

 

RESOLVED –

(a)  That the projected provisional financial outturn for the Authority, as detailed within the submitted report, be noted, with the projected impact of COVID-19 on that position also being noted;

 

(b)  That with regard to the 2020/21 financial year, it be noted that the Authority is forecasting a balanced budget position.


21/04/2021 - Leeds Covid-19 Vaccine Health Inequalities Plan ref: 54026    Recommendations Approved

Decision Maker: Executive Board

Made at meeting: 21/04/2021 - Executive Board

Decision published: 23/04/2021

Effective from: 01/05/2021

Decision:

The Director of Public Health submitted a report providing an update on the Leeds Covid-19 Vaccination Programme’s approach towards mitigating inequalities and ensuring that all communities have access to the Covid-19 vaccine through the ‘Leeds Covid-19 Vaccine Health Inequalities Plan’.

 

With the agreement of the Chair, supplementary information in the form of Appendix 4 to the report had been circulated to Board Members following the despatch of the agenda, in order to provide Members with an update on the main work streams of the Health Inequalities Vaccination Programme, including headline Covid-19 vaccination uptake data for the city.

 

In introducing the report, the Executive Member highlighted the range of actions being taken with partners and established community networks to increase the vaccination uptake across all communities in Leeds, in order to maximise the benefit of the current vaccination programme with the overriding principle that no one is left behind. As part of the introduction it was noted that 50% of Leeds’ adult population had now received a first Covid vaccination.

 

Responding to a Member’s specific enquiry, the Board received further detail regarding the progress which had been made to date, and the range of work which continued in encouraging vaccination uptake in BAME communities, with specific reference being made to the older generation. It was noted as part of the discussion that this was an issue affecting other vaccinations and was not unique to the Covid programme. As such, it was highlighted that in addition to the approach being taken to address inequalities in the current Covid vaccination round, the programme of work moving forward would reflect the longer term nature of this issue. 

 

RESOLVED –

(a)  That the contents of the submitted report and appendices, together with the related ambitions, as set out within the report, be noted, together with Members’ comments on such matters;

 

(b)  That it be noted that the Director of Public Health is the senior responsible officer for the Leeds Covid-19 Vaccine Health Inequalities Plan;

 

(c)  That the Board’s continued support be provided in relation to the commitment of all directorates in delivering the Leeds Covid-19 Vaccine Health Inequalities Plan.


04/05/2021 - Traffic Management Capital Programme 2021/22 ref: 54025    

Approve the annual programme of Traffic Management Capital Schemes & authorise the detailed development, consultation, preparation & delivery of these scheme subject to the satisfactory completion of any necessary orders & statutory processes.

Decision Maker: Director of City Development

Decision published: 23/04/2021

Effective from: 12/05/2021

Decision:

The Chief Officer Highways and Transportation has:

i)  Reviewed and approved the prioritised list of Traffic Management Capital schemes to the sum of £210,000 as identified in Appendix A for the 2021/22 capital year allocation;

 

ii)  Approved the design, consultation and (subject to the making of any necessary Traffic Regulation Orders – be this Speed Limit, Waiting/ Movement Restriction Order or Experimental Order), the implementation of the approved programme of works as detailed in Appendix B of this report;

 

iii)  Given authority and requested the City Solicitor to advertise any Traffic Regulation Orders as listed in Appendix A (Speed Limit, Waiting/ Movement Restriction Order or Experimental Order and any related traffic calming measures and proposals pursuant to The Local Government Miscellaneous Provisions Act 1976 in relation to Hackney Carriages) as required to address/ resolve the problems identified for each scheme, and if no valid objections are received, to make, seal and implement the Orders and proposals as advertised;

 

iv)  Will receive such other further reports as may be needed to address any objections received to advertised Orders or other matters arising from the detailed scheme proposals; and

 

v)  gave authority to incur expenditure of £210,000 (inclusive of any legal fees, staff fees and works costs) which will be funded by way of £200,000 from the Traffic Management Capital Programme and £10,000 from a Flood Risk Management contribution; and to commence the detailed design, consultation and implementation of the schemes described in Appendix B of this report; and

 

vi)  approved the injection of a £10,000 contribution from Flood Risk Management into the Traffic Management Capital Programme 2021/22.

Wards affected: Headingley and Hyde Park; Horsforth; Kippax and Methley; Little London and Woodhouse; Morley North; Rothwell;

Lead officer: Nick Borras


04/05/2021 - City Centre Vehicle Access Management Scheme - Allocation of Funding for Hostile Vehicle Mitigation (HVM) Schemes ref: 54024    

Request authority to fund improvements to the City Centre Vehicle Access Management Scheme (CCVAMS) & introduce HVM measures on Call Lane.

Decision Maker: Director of City Development

Decision published: 23/04/2021

Effective from: 12/05/2021

Decision:

The Chief Officer Highways and Transportation has given authority to:

a)  spend £569,956 on improvements to the CCVAMS and

b)  inject up to £300,000 on Call Lane HVM measures to be delivered by the Council’s LPTIP team.

Wards affected: Burmantofts and Richmond Hill; Little London and Woodhouse;

Lead officer: James Gray


04/05/2021 - Implementation of the 2021/22 Urban Traffic Management Control (UTMC) General Traffic Signal Refurbishment Scheme ref: 54034    

Approval to Spend for the UTMC General Traffic Signal Refurbishment Scheme.

The proposed scheme comprises refurbishment of traffic signals equipment at various sites across the city. Older traffic signal equipment becomes unsupported and the frequency of faults increases. Refurbishing the equipment enables newer technology to be implemented which results in more efficient operation both in terms of energy consumption and delay to road users. It also enables greater benefits to be realised from wider investment programmes.

Decision Maker: Director of City Development

Decision published: 23/04/2021

Effective from: 12/05/2021

Decision:

 

The Chief Officer Highways and Transportation has:

a)  Noted the contents of this report; and

b)  Approved spending of £600,000 (inclusive of all works costs, fees and legal costs), from the Local Transport Plan Transport Policy Capital Programme for the purposes of the refurbishing existing ageing traffic signal equipment as part of the UTMC General Traffic Signal Refurbishment Scheme 2021/22.

Wards affected: Beeston and Holbeck; Burmantofts and Richmond Hill; Chapel Allerton; Farnley and Wortley; Garforth and Swillington; Gipton and Harehills; Hunslet and Riverside; Little London and Woodhouse; Morley South; Otley and Yeadon; Temple Newsam;

Lead officer: Joel Dodsworth


22/04/2021 - Request for approval to award a contract to Bellavail IMS Ltd through a waiver of Contracts Procedure Rules No 9.1 and 9.2 – High Value Procurements ref: 54022    Recommendations Approved

Decision Maker: Director of City Development

Decision published: 22/04/2021

Effective from:

Decision:

a) The Chief Officer (Highway and Transportation) approved the waiver of Contract Procurement Rule No 9.1 and 9.2 - High Value Procurements to allow Leeds City Council to enter into a contract directly with Bellavail IMS Ltd.
b) This is a proof of concept at nil cost to Leeds City Council.
Spend is capped at £120,000 over the contract term.

Wards affected: (All Wards);

Lead officer: Seamus Millar


22/04/2021 - Special Guardianship Support proposals ref: 54021    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 22/04/2021

Effective from:

Decision:

a) Confirm recommendations agreed within the one adoption West Yorkshire board for establishing a sub-regional policy.
b) Specific recommendations with regards to local arrangements specific to the Leeds offer for special guardianship orders agreed.
c) That revised policies and procedures are put in place along with service training to set establish the local authorities Special Guardianship Support Arrangements.

Wards affected: (All Wards);

Lead officer: Ruth Terry


22/04/2021 - Diversion of Thorner Footpath Nos. 6 and 7 and the Creation of a Footpath Between Thorner 5 and 6 ref: 54020    For Determination

Decision Maker: Director of Communities, Housing & Environment

Decision published: 22/04/2021

Effective from:

Decision:

The Natural Environment Manager authorised the City Solicitor:

(a) to make and advertise a Public Path Diversion Order in accordance with Section 119 of the Highways Act 1980, in respect of parts of Thorner Footpath Nos. 6 and 7 shown on the maps attached (Background Document A)
and
(b) to confirm the Order, subject to there being no objections or in the event of objections which cannot be withdrawn, for the order to be referred to the Secretary of State, Department of the Environment, Food and Rural Affairs for determination
and
(c) authorised the City Solicitor to enter into a Public Path Creation Agreement with the landowner in accordance with Section 25 of the Highways Act 1980 to create a public footpath between Thorner Footpath No. 5 and 6 with a width of 2.5 metres as shown on Background Document B.

Wards affected: (All Wards);

Lead officer: Claire Tregembo


22/04/2021 - Child Employment & Entertainment ref: 54019    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 22/04/2021

Effective from:

Decision:

• Issuing of child performance licences
• Issuing of Chaperone Licences
• Issuing of work permits for young people aged (13-16 years of age)

Wards affected: Various;

Lead officer: Alison Foster


22/04/2021 - Write Off of Bankruptcy, Debt Relief Order and Individual Voluntary Arrangements for Housing tenancies ref: 54018    Recommendations Approved

Decision Maker: Director of Communities, Housing & Environment

Decision published: 22/04/2021

Effective from:

Decision:

The Director of Communities, Housing and Environment approved the write off of irrecoverable Insolvency debts in the sum of £99,951.14 represented by 63 accounts.

Wards affected: Various;

Lead officer: Jo-Anne Arnett


22/04/2021 - Approval to issue the third year Grant Agreement to Screen Yorkshire following North and West Yorkshire Business Rates Pool approval. ref: 54017    Recommendations Approved

Decision Maker: Director of City Development

Decision published: 22/04/2021

Effective from:

Decision:

The Director of City Development has authorised the release of Year Three (of three) funds in the grant agreement drafted for Screen Yorkshire, which totals £175,000 from the Business Rates Pool. This is specifically approved by the business rates pool joint committee per the funding agreement for use in Film Office activities as per the grant agreement and Screen Yorkshire application.

The North and West Yorkshire Business Rates Pool have agreed to fund Yr 3 (2021/22) costs from the NWY Pool.

Screen Yorkshire has provided the necessary reporting over Yr 1 and 2 to accurately monitor the use of previous funding and complied with State Aid requirements. The BRP further instructs the Chief Officer Culture and Economy to carry out the duties / responsibilities as specified in the agreement in respect of further monitoring arrangements.

Wards affected: (All Wards);

Lead officer: Gareth Read


30/04/2021 - Award of Grants for Additional Drug Treatment Crime and Harm Reduction Activity ref: 54016    Recommendations Approved

Leeds City Council have been allocated a £881k grant from Public Health England for additional drug treatment crime and harm reduction activity. The aim of the grant scheme is to drive down the crime associated with the drug market, particularly acquisitive crime and violent crime, and the rise in drug-related deaths.

Approval is being sought to award grant agreements to organisations involved in drug and alcohol treatment and Integrated Offender Management (IOM) support services (including Forward Leeds & Change Grow Live (CGL)). 

Decision Maker: Director of Public Health

Decision published: 22/04/2021

Effective from: 11/05/2021

Decision:

The Director of Public Health has:-

Approved the allocation of £568,490 as a grant (payable in instalments) to Humankind to provide additional harm reduction, treatment, wellbeing and recovery support from 1 May 2021 to 31 March 2022.

 

Approved the allocation of £105,030 as a grant (payable in instalments) to Change Grow Live Services Ltd to provide additional support within criminal justice settings from 1 May 2021 to 31 March 2022.

 

Approved the allocation of £207,480 as a grant (payment in instalments) to St Anne’s Community Services to provide additional residential detox and / or rehabilitation provision from 1 May 2021 to 31 March 2022.

 

Noted that Commissioning Managers within the Adults & Health Commissioning Team will implement this decision.

Wards affected: (All Wards);

Lead officer: Kate Daly


21/04/2021 - Approval of a care plan to the value between £100,000 and £500,000 per annum ref: 54014    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 21/04/2021

Effective from:

Decision:

The Deputy Director, Children & Families agreed the recommendation of a report relating to the placement of a child/young person. The individual costs of the place are £228,873.35.
It is considered in the public interest that information contained in the report is exempt from publication as it relates to a vulnerable child or young person of the City and the actions being taken to enable that person to live in a safe environment.

Wards affected: Various;

Lead officer: Ruth Terry


21/04/2021 - Approval of a care plan to the value between £100,000 and £500,000 per annum ref: 54013    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 21/04/2021

Effective from:

Decision:

The Deputy Director, Children & Families agreed the recommendation of a report relating to the placement of a child/young person. The individual costs of the place are £212,586.43.
It is considered in the public interest that information contained in the report is exempt from publication as it relates to a vulnerable child or young person of the City and the actions being taken to enable that person to live in a safe environment.

Wards affected: Various;

Lead officer: Ruth Terry


21/04/2021 - Approval of a care plan to the value between £100,000 and £500,000 per annum ref: 54012    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 21/04/2021

Effective from:

Decision:

The Deputy Director, Children & Families agreed the recommendation of a report relating to the placement of a child/young person. The individual costs of the place are £223,698.07.
It is considered in the public interest that information contained in the report is exempt from publication as it relates to a vulnerable child or young person of the City and the actions being taken to enable that person to live in a safe environment.

Wards affected: Various;

Lead officer: Ruth Terry


21/04/2021 - Approval of a care plan to the value between £100,000 and £500,000 per annum ref: 54011    Recommendations Approved

Decision Maker: Director of Children and Families

Decision published: 21/04/2021

Effective from:

Decision:

The Deputy Director, Children & Families agreed the recommendation of a report relating to the placement of a child/young person. The individual costs of the place are £184,061.68.
It is considered in the public interest that information contained in the report is exempt from publication as it relates to a vulnerable child or young person of the City and the actions being taken to enable that person to live in a safe environment.

Wards affected: Various;

Lead officer: Ruth Terry


21/04/2021 - The Re-Designation of the Carlton Village Neighbourhood Forum ref: 54010    Recommendations Approved

Decision Maker: Chief Planning Officer

Decision published: 21/04/2021

Effective from:

Decision:

The Chief Planning Officer has re-designated the Carlton Village Neighbourhood Forum.

Wards affected: Rothwell;

Lead officer: Emma Lewis


21/04/2021 - The Re-Designation of the Rothwell Neighbourhood Forum ref: 54009    Recommendations Approved

Decision Maker: Chief Planning Officer

Decision published: 21/04/2021

Effective from:

Decision:

The Chief Planning Officer has re-designated the Rothwell Neighbourhood
Forum.

Wards affected: Rothwell;

Lead officer: Caroline Harris


04/05/2021 - Approval to award a contract for Whole House Energy Efficiency Improvements on the Holt Park estate to ENGIE Regeneration Ltd under the Better Homes Yorkshire (BHY) Framework ref: 54015    Recommendations Approved

Decision Maker: Director of Communities, Housing & Environment

Decision published: 21/04/2021

Effective from: 04/05/2021

Decision:

The Director of Communities, Housing and Enviornment:
• Approved the award of a contract to ENGIE Regeneration Ltd to undertake energy efficient retrofits for a contract sum of £8.87m to 190 low rise properties on the Holt Park estate.
• Noted that this follows a procurement via the Better Homes Yorkshire (BHY) framework and that it is proposed that these works will commence in April 2021 and be completed in the current financial year.
• Recognised that Appendix 1 should be designated exempt from publication.

Wards affected: Adel and Wharfedale;

Lead officer: Paul Rounding


26/04/2021 - West Yorkshire Urban Traffic Management and Control (UTMC) Element C ref: 53999    

Funding to create a new ‘Central Hub’ for WY UTMC in Leeds has been approved at WYCA Investment Committee on 4th March 2021.

The new Central Hub will enable improved management of traffic on the road network across the city and is a key part of a larger scheme to improve consistency of approach to management of the KRN across West Yorkshire.

The Central Hub will also provide a dedicated space for training new engineers in a specialist discipline and the location, Leeds City Centre, will also aid future recruitment of apprentices and graduates through links with the colleges and universities.

This decision relates to approval to proceed with signing an associated Funding Agreement with WYCA and to inject the funding into the LCC Capital Programme.

Decision Maker: Director of City Development

Decision published: 16/04/2021

Effective from: 05/05/2021

Decision:

The Chief Officer Highways and Transportation approved entry into a Funding Agreement, for Element C of the WY UTMC project, with West Yorkshire Combined Authority in the sum of £555,000.

The Chief Officer Highways & Transportation gave authority to inject £555,000 into the Highways Capital Programme funded by pre-approved WYCA (West Yorkshire Combined Authority) grant funding.

The Chief Officer Highways & Transportation approved spending of £555,000 (inclusive of all works costs, fees and legal costs), funded by pre-approved WYCA (West Yorkshire Combined Authority) grant funding.

Wards affected: (All Wards);

Lead officer: Joel Dodsworth


21/04/2021 - Procurement Strategy Report in connection with the provision of Metering and Billing Services ref: 53986    

In relation to the implementation of a procurement exercise as required under CPR 3.1.6. Value of the contract will be Circa £980,000 and will provide the provision for Metering and Billing services across Leeds City Council properties.

Decision Maker: Director of Communities, Housing & Environment

Decision published: 13/04/2021

Effective from: 29/04/2021

Decision:

The Director of Communities, Environment & Housing noted the contents of this report and approved the recommended procurement route of a direct call-off to Switch2 Energy Limited using National Framework Partnerships Credit Metering Framework. The proposed contract will have a total value of £700,000 over 5 years from 17th June 2021 to 16th June 2026 with no option to extend.

Wards affected: (All Wards);

Lead officer: Adam Crampton